Skip to main content
CityRuleLookup

Kansas Statewide Rule

Kansas Solar Panel Grid-Connection and Net Metering Law

Some RestrictionsApplies statewide across Kansas (2026)

Key Facts

Statute
K.S.A. 66-1263 to 66-1271
Regulator
Kansas Corporation Commission
Building permit
Local city/county, not statewide
Required device
UL-listed automatic disconnect
Applies to
Investor-owned utility customers
Last verified: July 31, 2026

Summary

Kansas issues no statewide solar building permit: cities and counties handle that. But every grid-tied rooftop system must meet the Net Metering and Easy Connection Act's interconnection standards and win the utility's approval of a UL-listed automatic disconnect before it energizes.

66-1264. Definitions. ... (b) "Customer-generator" means the owner or operator of a net metered facility that: ... (3) is interconnected and operates in parallel phase and synchronization with an affected utility and is in compliance with the standards established by the affected utility; ... and (5) contains an underwriter laboratories listed mechanism, approved by the utility, that automatically disables the unit and interrupts the flow of electricity back onto the utility's electricity lines in the event that service to the customer-generator is interrupted.

Full Breakdown

The Net Metering and Easy Connection Act (K.S.A. 66-1263 through 66-1271) governs connecting customer-owned solar to the grid statewide. Under K.S.A. 66-1264, a customer-generator must operate in parallel phase and synchronization with its investor-owned utility, comply with that utility's standards, and install an underwriter-laboratories-listed mechanism, approved by the utility, that automatically disables the unit and cuts export back onto the lines if utility service is interrupted. The Kansas Corporation Commission administers the act. Building permits for the panels, racking, and wiring come from your city or county building department, not the state.

Violations & Penalties

Energizing a grid-tied array without utility approval or the required UL-listed automatic disconnect violates the interconnection standards; the utility can refuse or revoke parallel-operation service and disconnect the system until it complies.

Frequently Asked Questions

Does Kansas require a statewide solar permit?
No. Kansas has no statewide solar building permit; your city or county building department issues it. State law governs only grid interconnection under the Net Metering and Easy Connection Act.
What does Kansas require to connect solar to the grid?
Under K.S.A. 66-1264, the system must operate in parallel with your investor-owned utility, meet its standards, and include a UL-listed device that automatically disconnects export if utility service is interrupted.
Who enforces Kansas net metering rules?
The Kansas Corporation Commission administers the Net Metering and Easy Connection Act for investor-owned electric utilities across the state.

Sources

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.