Missouri Statewide Rule

Missouri Solar Interconnection: Net Metering and Easy Connection Act

Some RestrictionsApplies statewide across Missouri (2026)

Key Facts

Statute
RSMo 386.890
System cap
One hundred kilowatts
Simple-form threshold
Ten kilowatts or less
Administered by
Missouri Public Service Commission
Safety standards
NEC, NESC, IEEE, UL
Last verified: July 31, 2026

Summary

Missouri's Net Metering and Easy Connection Act (RSMo 386.890) gives every utility customer the right to connect a solar system up to one hundred kilowatts, using a standardized simple interconnection application for systems of ten kilowatts or less.

This section shall be known and may be cited as the 'Net Metering and Easy Connection Act'. ... A customer-generator's facility shall be equipped with sufficient metering equipment that can measure the net amount of electrical energy produced or consumed by the customer-generator. ... For systems of ten kilowatts or less, the application process shall use an all-in-one document that includes a simple interconnection request, simple procedures, and a brief set of terms and conditions.

Full Breakdown

RSMo 386.890, the 'Net Metering and Easy Connection Act,' requires all Missouri retail electric suppliers to offer net metering to customer-generators with solar systems up to one hundred kilowatts. For systems of ten kilowatts or less, the utility must accept a single all-in-one document combining the interconnection request, procedures, and terms. The customer's facility must carry metering equipment that measures the net energy produced or consumed. Equipment must meet the National Electrical Code, National Electrical Safety Code, IEEE, and UL standards, plus any local code authority. The Missouri Public Service Commission administers the program through rule 20 CSR 4240-20.065; local jurisdictions still issue the building and electrical permits.

Violations & Penalties

A customer cannot back-feed the grid until the retail electric supplier approves the interconnection agreement. Systems that skip interconnection or fail the required NEC, NESC, IEEE, and UL safety standards can be denied connection or disconnected by the utility.

Frequently Asked Questions

Do I need a state permit to install solar panels in Missouri?
No statewide solar permit exists. RSMo 386.890 grants interconnection rights; your local city or county issues the building and electrical permits, and your utility approves the grid interconnection agreement.
How large a solar system can I net meter?
Up to one hundred kilowatts of generating capacity qualifies for net metering under the Net Metering and Easy Connection Act.
Is the interconnection process simplified for small systems?
Yes. For systems of ten kilowatts or less, the utility must use an all-in-one document combining the interconnection request, simple procedures, and terms and conditions.