South Carolina Statewide Rule
South Carolina Sediment and Erosion Control Standards
Key Facts
- Governing statute
- SC Code 48-14, Reg 72-300
- Inspection frequency
- Every 7 days minimum
- Stabilization standard
- 70 percent vegetative cover
- Rain trigger inspection
- 0.5 inch event
- Maximum penalty
- $1,000 per day
Summary
South Carolina's Sediment Reduction Act sets statewide minimum erosion and sediment-control standards for construction sites. SCDES (formerly DHEC) enforces uniform technical requirements that apply regardless of local jurisdiction.
The department shall implement a statewide erosion and sediment reduction and stormwater management program as follows: (1) The department is designated as the state agency responsible for developing, coordinating, and promoting erosion and sediment reduction and stormwater management programs in the State. (2) The department must develop general guidelines for reducing erosion and sedimentation and improving stormwater management for use by conservation districts, local government, landowners, and land users of the State. The department must publicize and promote these guidelines through information and education programs.
Full Breakdown
Under SC Code Title 48, Chapter 14 and Regulation 72-300, all land disturbance of one acre or greater requires erosion and sediment-control best management practices including silt fences, sediment basins, stabilized construction entrances, and prompt seeding or stabilization. The SCDES Stormwater BMP Manual specifies technical design criteria that must be met. Sites must maintain controls until permanent stabilization of 70 percent vegetative cover. Inspections are required at least every seven days and after rain events of 0.5 inches or more.
Violations & Penalties
Failure to implement controls is enforceable by SCDES with civil penalties up to $1,000 per day per violation. Stop-work orders and mandatory restoration may be ordered, and repeat violators face escalated enforcement.
Frequently Asked Questions
Are erosion controls required after construction is complete?
Can my contractor ignore controls during dry weather?
Who can be penalized for sediment violations?
Sources
See something wrong?