Orangeburg County, SC Swimming Pools & Spas: Pool Permits (2026)
Swimming pool permit rules in Orangeburg County, SC, also covering above-ground pools, in-ground pools, and spa installations, set fencing, barrier, alarm, and inspection requirements.
Key Facts
- Pool permit combo
- Building + Electrical + Plan Review
- Governing fee schedule
- Sec. 6-14.2
- Underlying permit duty
- Sec. 6-15
- Plan review rate
- 25% of residential permit fee
- Unpermitted work
- Fee doubled under Sec. 6-18
- Appeals body
- Buildings Regulations Board of Appeals
Summary
Orangeburg County's Sec. 6-14.2 permit fee schedule lists swimming pools as requiring a building permit, an electrical permit and plan review. Sec. 6-15 requires that permit before pool construction covered by the adopted building or residential code begins anywhere in the unincorporated county.
Sec. 6-14.2. - Building permit rates; demolition rates; house/building moving rates; and temporary signs. ... Other Permitting Fees ... Swimming Pools Building + Electrical + Plan Review
Full Breakdown
Sec. 2 of the county code, adopted alongside the building permit rate schedule, lists "Swimming Pools" among the "Other Permitting Fees" and specifies that a pool project requires Building plus Electrical plus Plan Review, meaning the applicant must secure a building permit and an electrical permit and submit plans for review rather than pay a single flat fee. That plan review requirement tracks the general plan review fees Sec. 2 sets for other work: 25% of the permit fee for residential projects and 50% for commercial projects.
The underlying permit duty comes from Sec. 6-15, which requires any owner, agent or contractor who wants to construct, enlarge, alter or repair a structure regulated by the codes adopted in Sec. 6-14, including the 2024 International Residential Code and International Building Code, to apply to the building official and obtain a permit before starting work. Sec. 6-16 bars the building official from issuing that permit until the fee is paid, and Sec. 6-18 doubles the fee if pool construction starts before a permit is obtained.
Because the permit table treats pools as needing an electrical permit as well, an in-ground or above-ground pool with pumps, lighting or bonding wiring also triggers the National Electrical Code permit obligation. Appeals from a building official's pool-permit decision go to the Buildings Regulations Board of Appeals under Sec. 6-19.
Violations & Fines
Building a pool without first obtaining the required building and electrical permits doubles the fee owed under Sec. 6-16 and Sec. 6-18, and the work remains subject to the full inspection and compliance requirements of chapter 6. The building official may issue a notice of violation or a stop-work order under the chapter's general enforcement sections.
Frequently Asked Questions
What permits do I need to build a swimming pool in unincorporated Orangeburg County?
Is there a separate plan review fee for a pool?
What happens if I build a pool before getting a permit?
Sources & Official References
Other rules in Orangeburg County
Compare Orangeburg County to another location·View the South Carolina swimming pools & spas overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.