Key Facts

DT-1 height range
24 ft minimum, 90 ft max (150 ft with ground retail)
DT-1 front setback
None for first 4 stories, 20 ft at 9+ stories
Nonresidential glazing
40% first floor, 20% upper floors, front facade
Frontage occupied by wall
100% interior lots, 80% corner lots
DT-2 height
35 ft residential, 75 ft others, 130 ft with retail
Enforcing office
City Manager / Development Services Department

Summary

Fayetteville's Downtown 1 and Downtown 2 zoning districts set mandatory design rules for new buildings: minimum ground-floor window coverage, tight or zero front setbacks, and height ranges tied to story count. The City Manager enforces the standards through the Building and Zoning Permit process before construction begins.

The Downtown 1 (DT-1) District is established and intended to encourage the urban form and architectural character found in the traditional downtown area as well as promote redevelopment that will make the downtown area a more diverse and vibrant mixed-use urban center...Front setback, min. (ft.) None for first 4 stories; 10 for stories 5-8; 20 for stories 9+...Nonresidential uses: Minimum of forty percent (40%) of the first floor and twenty percent (20%) of the upper floors on the front facade shall have window/door fenestration. Tinted or mirrored glass is prohibited on the front facade. Side elevations which can be seen from the public view shall have a minimum of twenty percent (20%) window/door fenestration.

Full Breakdown

The Downtown 1 (DT-1) District, adopted by Ordinance No. S2022-007, is built to encourage traditional downtown urban form: buildings must be at least 24 feet tall and can rise to 90 feet, or 150 feet if street-level restaurant or retail space is included. Front setbacks run from none for the first four stories to 20 feet once a building reaches nine or more stories. Interior lots must occupy 100 percent of the primary street frontage with building wall; corner lots 80 percent. Nonresidential ground floors need at least 40 percent window and door fenestration on the front facade, 20 percent on upper floors, and tinted or mirrored glass is barred from the front facade entirely.

Side walls visible from public view need at least 20 percent fenestration. Residential fronts need a minimum of 30 percent glazing on publicly visible elevations. The neighboring DT-2 district applies a parallel framework: 35-foot height cap for single-family residential portions and 75 feet for other uses (up to 130 feet with ground-level dining or retail), plus the same 40/20 percent glazing formula. Government offices, museums, passenger terminals, and religious institutions are exempt from the downtown maximum front-setback rule if the setback area is landscaped or hardscaped for pedestrian use. 12, Building and Administrative Zoning Permits.

Violations & Fines

The City Manager will not issue a Building Permit or Certificate of Occupancy for downtown construction that fails the DT-1/DT-2 glazing, setback, or height standards. A permit denial under Section 30-2.C.12 may be appealed to the Zoning Commission under Section 30-2.C.18; a Building Permit automatically expires if work is not started within six months of issuance under N.C.G.S. § 160D-1111.

Frequently Asked Questions

Can I build a downtown Fayetteville storefront with no front setback?
Yes for the first four stories in the DT-1 district; Section 30-3.E.10 sets no minimum front setback there, rising to 10 feet for stories five through eight and 20 feet for stories nine and above. A maximum setback also applies to keep buildings close to the sidewalk.
How much window glass does a downtown storefront need?
Nonresidential buildings in DT-1 and DT-2 need at least 40 percent window or door fenestration on the front facade's first floor and 20 percent on upper floors, per Section 30-3.E.10. Tinted or mirrored glass is prohibited on the front facade.
Is my downtown project reviewed before I can build?
Yes. Section 30-2.C.12 requires the City Manager to confirm compliance with the DT-1/DT-2 design standards before issuing a Building Permit or Administrative Zoning Permit; denials can be appealed to the Zoning Commission under Section 30-2.C.18.

Sources & Official References

Other rules in Fayetteville

All Fayetteville rules

Compare Fayetteville to another location·View the North Carolina zoning overlays & bonuses overview

Get notified when Downtown Design Guide in Fayetteville, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.