Key Facts

Accessory structures
Fully exempt under § 22D.020.040(1)(b)
ADUs under Ch 22C.180
Fully exempt under § 22D.020.040(1)(g)
Single-family/middle housing fee
$1,251 per housing unit
Multifamily fee
$884 per housing unit
Claim deadline
No later than building permit application
Appeal path
Title 22G administrative appeal

Summary

Marysville exempts accessory structures and city-approved accessory dwelling units from its park, recreation, open space and trail impact fees. Marysville Municipal Code § 22D.020.040(1)(b) exempts accessory structures outright, and (1)(g) exempts ADUs approved under Chapter 22C.180 MMC, even though a standalone single-family or middle-housing unit otherwise owes $1,251 per housing unit under the city's adopted fee schedule.

(1) The following are excluded from the requirement to pay some or all of the required impact fees: ... (b) The construction of structures accessory to a residence is exempt from the requirement to pay all impact fees. (c) Parking garages and building space which is constructed solely to park motor vehicles which are not owned, leased or rented by a business or part of a stock in trade are exempt from the requirement to pay all impact fees. (d) Temporary uses and structures authorized by Chapter 22C.110 MMC are exempt from the requirement to pay all impact fees. ... (g) Accessory dwellings approved by the city under Chapter 22C.180 MMC. (2) Any claim of exemption shall be made no later than the time of application for a building permit. If a building permit is not required for the development activity, the claim shall be made when the fee is tendered. Any claim not made when required by this section shall be deemed waived.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4922912; v1 updated 2026-06-08; through 06-08-2026).

Full Breakdown

Marysville imposes park, recreation, open space and trail impact fees under Chapter 22D.020 MMC, adopted under RCW 82.02.050(2) as part of the city's Growth Management Act comprehensive plan. Section 22D.020.030 requires payment before a building permit issues for most new development, with fees set by § 22D.020.050 at $1,251 per housing unit for single-family homes, mobile and manufactured homes, and middle housing, and $884 per unit for multifamily housing.

Section 22D.020.040 exempts several project types from all or part of that fee. Subsection (1)(b) exempts the construction of structures accessory to a residence from the requirement to pay any impact fees. Subsection (1)(g) separately exempts accessory dwelling units approved by the city under Chapter 22C.180 MMC. Other exemptions in the same subsection cover the replacement of an existing structure without added floor space or dwellings (if a permit is filed within three years of removal), stand-alone vehicle parking garages, temporary uses under Chapter 22C.110 MMC, and development activity already mitigated under SEPA. Subsection (2) requires the property owner to claim any exemption no later than the building permit application; the city treats a late claim as waived. Section 22D.020.080 lets a person challenge a fee decision through the same appeal process that applies to the underlying permit, or through a Title 22G administrative appeal where no other process exists, and permits payment of a disputed fee under written protest so the permit can still issue while the dispute proceeds.

Violations & Fines

Missing the exemption claim deadline waives it under § 22D.020.040(2), and a non-exempt project that skips payment cannot get its building permit issued under § 22D.020.030; the city may still refer formula errors to the mayor and city council for correction under § 22D.020.080(1).

Frequently Asked Questions

Are accessory dwelling units exempt from Marysville impact fees?
Yes. Marysville Municipal Code § 22D.020.040(1)(g) exempts accessory dwelling units approved by the city under Chapter 22C.180 MMC from the park, recreation, open space and trail impact fee entirely, on top of the separate exemption for accessory structures generally.
What impact fee would a new single-family house owe if it were not exempt?
Section 22D.020.050(2) sets the park, recreation, open space and trail impact fee at $1,251 per housing unit for single-family homes, mobile and manufactured homes, and middle housing, and $884 per unit for multifamily housing; ADUs and accessory structures are carved out of that schedule.
When do I have to claim the ADU or accessory structure exemption?
Section 22D.020.040(2) requires the claim no later than the time of the building permit application, or when the fee would otherwise be tendered if no permit is required. A claim made after that point is deemed waived.
Can I dispute a Marysville impact fee I think is wrong?
Yes. Section 22D.020.080 lets you appeal the underlying permit decision, or bring a Title 22G administrative appeal if no other process applies, and you can pay the fee under written protest to get your permit while the dispute is pending.

Sources & Official References

Other rules in Marysville

All Marysville rules

Compare Marysville to another location·View the Washington accessory structures overview

Get notified when ADU Impact Fees in Marysville, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

ADU Impact Fees in Nearby Cities

How other cities in Snohomish County handle adu impact fees.

Lynnwood, WA
Some Restrictions
Everett, WA
Some Restrictions