Key Facts

Permit issued by
County Building Inspector
Application turnaround
7 days for complying applicants
Permit validity
Void 6 months after issuance if unstarted
Exempt uses
Agricultural and utility uses (Ch. 18.115 BHCC)
First-offense fine
$250.00, rising to $750.00 for repeat offenses
Scope
Unincorporated Black Hawk County only

Summary

In unincorporated Black Hawk County, Iowa, no building may be erected, altered or occupied without a permit issued by the County Building Inspector. BHCC 18.110.010 requires permits before construction begins, applications process within seven days, and permits expire if work has not started within six months. Agricultural and utility uses are exempt under Chapter 18.115.

These county ordinances apply to unincorporated areas of Black Hawk County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Building permits shall be required in accordance with the following, except that no permit shall be required for agricultural or utility uses in accordance with Chapter 18.115 BHCC: ... A. No land shall be occupied or used, and no building hereafter erected or structurally altered shall be occupied or used in whole or in part for any purpose whatsoever, until a building permit is issued by the County Building Inspector, stating that the building and use comply with the provisions of this chapter. ... D. In accordance with this section, building permits shall be obtained from the County Building Inspector before starting or proceeding with the erection, construction, moving in, or the structural alteration of a building or structure. Building permits shall be issued to complying applicants within seven days after application is made and appropriate records and copies of permits shall be maintained as a matter of public record. ... E. A building permit shall become null and void six months after the date on which it is issued unless within such six-month period construction, building, moving, remodeling or reconstruction of a structure is commenced or a use is commenced.

Full Breakdown

010, part of Title 18 (Agricultural Land Preservation and Zoning), governs unincorporated Black Hawk County only, not Waterloo, Cedar Falls, Evansdale, Hudson, La Porte City, Dunkerton, Gilbertville, Elk Run Heights or Raymond, each of which enforces its own building code. The rule bars occupying or using any land, or erecting or structurally altering any building, until the County Building Inspector issues a permit confirming compliance with Title 18. A separate permit is required for any change of use in an existing building. Nonconforming uses already lawfully established may continue, but discontinuance can be forced where public safety requires it.

020. Complying applications must be turned around within seven days, and the county keeps permit records public. 010(E) voids it automatically six months after issuance unless construction, moving or reconstruction has actually started, so a stalled project must reapply. 115 BHCC exempts agricultural and utility uses from the permit requirement entirely, reflecting the county's farmland-preservation focus. 010 building permit.

Violations & Fines

Building without the required permit, or failing to comply with Title 18's conditions, is a civil infraction under BHCC Section 18.145.010: a $250.00 fine for a first offense, $500.00 for a second, and $750.00 for a third or later offense, with each day of continued noncompliance counted as a separate violation. The county can also pursue any other lawful remedy to stop or correct the work.

Frequently Asked Questions

Do I need a permit to build in unincorporated Black Hawk County?
Yes. Under BHCC Section 18.110.010, no land may be occupied and no building erected or structurally altered until the County Building Inspector issues a permit confirming the work complies with Title 18. This applies only outside the county's cities; Waterloo, Cedar Falls and the other municipalities enforce their own separate building permit rules.
How long is a Black Hawk County building permit good for?
Six months. BHCC Section 18.110.010(E) voids a permit automatically if construction, moving, remodeling or reconstruction has not begun within six months of issuance, so a delayed project needs a new application before work can start.
Are farms exempt from the county building permit requirement?
Yes. BHCC Section 18.110.010 exempts agricultural and utility uses from the county's building permit requirement, pointing to the special exemptions listed in Chapter 18.115 BHCC, consistent with Title 18's overall agricultural land preservation and zoning framework for the unincorporated county.
What happens if I build without a permit in unincorporated Black Hawk County?
It is a county infraction under BHCC Section 18.145.010: a $250.00 civil fine for a first offense, $500.00 for a second and $750.00 for a third or later offense, with each additional day of noncompliance treated as its own separate violation.

Sources & Official References

Other rules in Black Hawk County

All Black Hawk County rules

Compare Black Hawk County to another location·View the Iowa building safety overview

Get notified when Building Permits in Black Hawk County, IA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.