Key Facts

Permit issued by
Zoning Officer, Bristol Township
Governing sections
§§ 205-171 to 205-175 and Chapter 84
Permit validity
Work must start within six months or permit is void
Extension
Annual, no added fee, aggregate not more than three years
Certificate of occupancy
No fee, void 90 days after issuance if unused
Civil judgment
Not more than $500 per day of violation

Summary

In Bristol Township, no structure can be erected, constructed, reconstructed, altered, added to, razed or removed, and no building occupied or changed in use, until the necessary permits are secured from the Zoning Officer. Section 205-171 also requires inspection and approval of the finished work, and the Township administers the state Construction Code under § 84-1.

§ 84-1. Administration and enforcement of state law. The Township hereby elects to administer and enforce the provisions of the Code Act, Act 45 of 1999, 35 P.S. § 7210.101-7210.1103, as amended from time to time and its regulations. ... § 205-171. Permits, inspection and approval required. ... Hereafter, no use listed in § 205-15 or 205-16 may be established or changed, no structure shall be erected, constructed, reconstructed, altered, added to, razed or removed, and no building used or occupied, or changed in use, until all necessary permits have been secured from the Zoning Officer. ... No permit shall be considered as complete or as permanently effective until the Zoning Officer has noted on the permit that the work or occupancy and use have been inspected and approved as being in conformity with the provisions of this chapter.

Full Breakdown

Section 205-171 of the Bristol Township zoning chapter sets the trigger. No use listed in § 205-15 or 205-16 can be established or changed, no structure can be erected, constructed, reconstructed, altered, added to, razed or removed, and no building can be used, occupied or changed in use, until all necessary permits have been secured from the Zoning Officer. When the work is done, the applicant must notify the Zoning Officer, and no permit is complete or permanently effective until the Zoning Officer notes that the work or occupancy has been inspected and approved as conforming to the chapter. Only one single principal use per building is allowed. Signs greater than two square feet need a building permit under § 205-169, and every accessory home occupation needs one under § 205-16.

Applications under § 205-172 are made in writing by the owner, tenant, vendee under contract of sale or authorized agent, on a Township form filed with the Zoning Officer. The Zoning Officer can require a statement of proposed use, a scaled site layout showing buildings and property lines, open spaces and buffer yards, tree protection, parking and loading, sidewalks, sewage and water provisions, and an erosion and sedimentation plan. New on-site sewage disposal needs Bucks County Department of Health approval before a permit issues, and all buildings must comply with the Township Building Codes. The permit fee follows the schedule adopted by resolution of Council under § 205-175.

Under § 205-173, work must commence within six months of issuance or the permit is null and void, though construction can be extended annually without additional fees for an aggregate of not more than three years if it commenced in the first one-year period. Under § 205-174, a certificate of occupancy is required before a new or changed building is used. It carries no fee and becomes void 90 days from issuance unless occupancy begins. Chapter 84 adds that the Township elects to administer and enforce the Code Act, Act 45 of 1999, adopts the Construction Code by reference as the Township Construction Code, and sets fees through Township Council. Under § 84-3, enforcement can run through a Township employee, third-party agencies or an agreement with the Pennsylvania Department of Labor and Industry for structures other than one-family or two-family dwelling units.

Violations & Fines

The Zoning Officer enforces the permit requirement through an enforcement notice under § 205-204, giving five days to commence compliance and 30 days to complete it, with a 30-day appeal to the Zoning Hearing Board. Under § 205-205, a judgment of not more than $500 plus court costs and reasonable attorney fees is imposed for each day of violation, and each day the violation continues counts as a separate violation. The Zoning Officer can also revoke any order or building permit issued under a mistake of fact or contrary to the law or the chapter.

Frequently Asked Questions

Do I need a permit to alter or remove a building in Bristol Township?
Yes. Section 205-171 lists erected, constructed, reconstructed, altered, added to, razed and removed structures, and it also covers any building occupied or changed in use. All necessary permits must be secured from the Zoning Officer first, and the Zoning Officer must inspect and approve the finished work before the permit counts as complete.
How long is a Bristol Township building permit valid?
Work must commence within six months of issuance, or the permit is null and void under § 205-173. For erection or construction of a building, the right to proceed can be extended annually without additional fees for an aggregate period of not more than three years, provided construction began within the first one-year period.
Do I need a certificate of occupancy?
Yes. Under § 205-174, no structure erected, constructed, reconstructed, extended or moved, and no land or building changed in use under a building permit, can be occupied until the Zoning Officer issues one. There is no fee, and the certificate becomes void 90 days from issuance unless occupancy begins. Businesses open to the public also need one from the Pennsylvania Department of Labor and Industry.
Who enforces the Uniform Construction Code in Bristol Township?
Under § 84-1 the Township elects to administer and enforce the Code Act, Act 45 of 1999. Under § 84-3, Township Council decides by resolution whether a designated Township employee, third-party agencies, other municipalities or the Pennsylvania Department of Labor and Industry carry out plan review, inspections and enforcement. A Board of Appeals is established by resolution under § 84-4.

Sources & Official References

Other rules in Bristol Township

All Bristol Township rules

Compare Bristol Township to another location·View the Pennsylvania building safety overview

Get notified when Building Permits in Bristol Township, PA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.