Key Facts

Permit required
Before any construction or development anywhere in Bristol Township
Exempt work
Minor repairs to existing buildings or structures
Inspections
As many during and on completion of work as are necessary
Permit deadlines
Start within 180 days, finish within 12 months
Fine
$25 to $600 plus costs of prosecution
Responsible official
Director of Building, Planning and Development (§ 68-7)

Summary

In Bristol Township, Pennsylvania, anyone who builds or develops anywhere in the Township needs a permit under Chapter 68, and § 68-9 requires the Floodplain Administrator or another authorized official to inspect the premises during construction and on completion, as many times as are necessary. Work that departs from the permit application gets the permit revoked and reported to Township Council.

D. During the construction period, the Floodplain Administrator or other authorized official shall inspect the premises to determine that the work is progressing in compliance with the information provided on the permit application and with all applicable municipal laws and ordinances. He/she shall make as many inspections during and upon completion of the work as are necessary. E. In the discharge of his/her duties, the Floodplain Administrator shall have the authority to enter any building, structure, premises or development in the identified floodplain area, upon presentation of proper credentials, at any reasonable hour to enforce the provisions of this chapter. F. In the event the Floodplain Administrator discovers that the work does not comply with the permit application or any applicable laws and ordinances, or that there has been a false statement or misrepresentation by any applicant, the Floodplain Administrator shall revoke the permit and report such fact to the Council for whatever action it considers necessary.

Full Breakdown

Chapter 68 of the Bristol Township Code is the Township's floodplain chapter, but its permit and inspection rules reach construction and development anywhere in the Township. Section 68-3 makes it unlawful to undertake any construction or development without a permit from the Floodplain Administrator, and § 68-8 repeats that a permit is required before work starts in any area of the Township. Minor repairs to existing buildings or structures are exempt under § 68-3(B).

The Floodplain Administrator is the Director of Building, Planning and Development (§ 68-7). That official can delegate duties to qualified technical personnel, plan examiners and inspectors, or contract with another agency, and the Township Manager steps in if the post is vacant. Before issuing a permit, § 68-9 requires a check that the work conforms to all other codes and ordinances and that required state and federal permits are in hand. For existing structures the repair history is reviewed first.

The inspection duty sits in § 68-9(D): during construction the Administrator or another authorized official inspects the premises to confirm the work follows the permit application and every applicable municipal law, with as many inspections during and on completion of the work as are necessary. Section 68-9(E) allows entry into any building, structure, premises or development in the identified floodplain area at any reasonable hour on presentation of proper credentials. Records of permitting, inspection and enforcement are kept in perpetuity (§ 68-9(G)).

A placard showing the permit number and issue date, signed by the Administrator, must be displayed on the premises while construction is in progress (§ 68-14). Work must begin within 180 days of issuance and finish within 12 months, or the permit expires unless the Administrator grants a written extension (§ 68-15). No change to the application or plans is allowed without written consent (§ 68-13).

Separately, Chapter 84 has the Township elect to administer and enforce the state Code Act (Act 45 of 1999). Under § 84-3, Township Council decides by resolution whether enforcement runs through a designated employee, third-party agencies, other municipalities or the Pennsylvania Department of Labor and Industry for structures other than one-family or two-family dwellings. Section 84-9 leaves fees to Council, and § 84-4 sets up a Board of Appeals.

Violations & Fines

Under § 68-16, the Floodplain Administrator serves written notice stating the reasons and allowing a reasonable time not to exceed 30 days to comply. Failing to comply with Chapter 68 or a notice or order is a summary offense carrying a fine to Bristol Township of not less than $25 nor more than $600 plus costs of prosecution. Equity actions remain available, and a fine does not excuse the violation. Under § 68-9(F), non-conforming work or a false statement by an applicant means the permit is revoked and reported to Council.

Frequently Asked Questions

Who inspects construction in Bristol Township?
Section 68-9(D) assigns inspections to the Floodplain Administrator or another authorized official. The Administrator is the Director of Building, Planning and Development, who can delegate to qualified technical personnel, plan examiners and inspectors or contract with another agency under § 68-7. If the post is vacant, the Township Manager fulfills the duties.
How many inspections does a project get?
The code prints no fixed number. Section 68-9(D) says the Administrator or authorized official makes as many inspections during and upon completion of the work as are necessary to confirm it follows the permit application and all applicable municipal laws and ordinances.
How long does a Bristol Township permit last?
Under § 68-15, work must begin within 180 days after the permit is issued and be completed within 12 months, or the permit expires. The Floodplain Administrator can grant a written time extension if the applicant submits a written request showing sufficient and reasonable cause.
Can an inspector enter my property?
Section 68-9(E) lets the Floodplain Administrator enter any building, structure, premises or development in the identified floodplain area at any reasonable hour, on presentation of proper credentials, to enforce Chapter 68. Section 68-9(D) separately directs inspection of the premises during the construction period.
Who decides how the Construction Code is enforced?
Township Council decides by resolution under § 84-3 whether to use a designated employee, third-party agencies, joint or contract arrangements with other municipalities, or the Pennsylvania Department of Labor and Industry for structures other than one-family or two-family dwellings. Council also sets the fees under § 84-9.

Sources & Official References

Other rules in Bristol Township

All Bristol Township rules

Compare Bristol Township to another location·View the Pennsylvania building safety overview

Get notified when Building Inspections in Bristol Township, PA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.