Clark County, IN Building Safety: Building Permits (2026)
Key Facts
- Permit required for
- construction, alteration, demolition, repair
- Work must start within
- 90 days of issuance
- New residential permit fee
- $25 (first 1,000 sq ft)
- Commercial design release
- required per I.C. 22-15-3-1
- No-permit penalty
- $100 fine plus double permit cost
Summary
Clark County requires a permit before any construction, alteration, demolition or repair of a building or structure in the unincorporated county. Permits issue through the Plan Commission office, and work must start within 90 days or the permit lapses.
§ 151.08 PERMIT REQUIRED. (A) A permit shall be obtained before beginning construction, alteration, demolition or repair of any building or structure, using forms furnished by the Building Commissioner. (B) All permits shall be issued in the office of the Plan Commission. (C) All work must commence within 90 days from date of issue of the permit.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2019 S-0: Code: Local legislation current through Ordinance 31-2014, passed 12-18-2014).
Full Breakdown
08 states plainly that a permit shall be obtained before beginning construction, alteration, demolition or repair of any building or structure, on forms furnished by the Building Commissioner, that all permits are issued in the office of the Plan Commission, and that all work must commence within 90 days from the date of issue. 07 requires a plot plan showing the applicant's name and address, all property lines and dimensions, a north arrow, driveway location, surrounding street names, existing and proposed structure sizes, ground slope direction, proposed setbacks from roads and property lines, and known easements.
C. 22-15-3-1 before a permit can issue. 09 requires that all work under a permit comply with every other applicable ordinance, and that fees for those other ordinances are paid in addition to the building permit fee. 10(A)(1) sets the building permit fee itself, starting at $25 for a new residential structure's first 1,000 square feet plus $2 per additional 100 square feet, $30 for a commercial structure's first 1,000 square feet plus $3 per additional 100 square feet, and set fees running from $15 to $40 for additions, accessory buildings, garages, demolitions, campers and pools.
16 makes it unlawful to erect, alter, repair, or demolish any building in the county, or to cause that to be done, contrary to the Building Code.
Violations & Fines
Building without a permit, or otherwise violating §§ 151.01 through 151.18, is fined not less than $50 nor more than $500 per violation under § 151.99(B), plus attorney fees and court costs, with each day of continued noncompliance a separate offense. Starting construction before a permit is issued adds a flat $100 fine, collected when the belated permit application is filed, plus double the normal permit fee.
Frequently Asked Questions
Do I need a permit to build an addition in unincorporated Clark County?
What information does my permit application need?
How long do I have to start work after my permit is issued?
What happens if I start building before getting a permit?
Sources & Official References
Other rules in Clark County
Compare Clark County to another location·View the Indiana building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.