Key Facts

Permit issued by
Building official
Small shed exemption
Under 120 square feet
Permit expires if unstarted
180 days
Plan review fee
25% of permit fee
Unpermitted work fee
2x to 4x normal permit fee

Summary

In the City of Council Bluffs, CBMC 13.01.301 requires a separate permit from the building official before erecting, altering, moving, repairing or demolishing any building, structure or building service equipment, with narrow exemptions such as small tool sheds under 120 square feet. The permit expires if work is not started within 180 days.

Permits Required. Except as specified in CBMC 13.01.301 Paragraph B, no building, structure or building service equipment regulated by this code and the technical codes shall be erected, constructed, enlarged, altered, repaired, moved, improved, removed, converted or demolished unless a separate, appropriate permit for each building, structure or building service equipment has first been obtained from the building official. Work Exempt from Permit. A permit shall not be required for the types of work in each of the separate classes of permit as listed below. ... Building Permits. A building permit shall not be required for the following: One-store detached accessory buildings used as tool and storage sheds, playhouses and similar uses, provided the floor area does not exceed one hundred twenty (120) square feet (11.15 m 2).

Full Breakdown

CBMC 13.01.301 sets the baseline rule: no building, structure or building service equipment covered by the technical codes may be erected, constructed, enlarged, altered, repaired, moved, improved, removed, converted or demolished without a separate, appropriate permit from the building official for each building, structure or piece of equipment. A short list of exemptions follows for minor work, including one-story detached tool sheds and similar accessory buildings under one hundred twenty square feet, retaining walls under four feet, small prefabricated pools, and minor roof repairs of one square of shingles or less, though separate plumbing, electrical or mechanical permits can still apply.

To obtain a permit under CBMC 13.01.302, the applicant files a written application identifying the work and property, states the construction valuation, and, for projects needing plans, submits drawings, computations and specifications that the building official reviews under CBMC 13.01.303 before issuing the permit; the contractor is responsible for securing the permit before construction begins. Fees under CBMC 13.01.304 are based on the International Code Council's Building Valuation Data, with local add-ons such as $2.60 per square foot for fire sprinkler systems and a twenty-five percent plan review fee on top of the permit fee.

A permit expires and becomes void if work has not started within one hundred eighty days, or is suspended for one hundred eighty days, and the building official may extend that deadline once, also for up to one hundred eighty days. Starting work without first obtaining a permit triggers an investigation fee of two to four times the normal permit fee under CBMC 13.01.304.

Violations & Fines

Doing permit-required work without one violates CBMC 13.01.206, which makes it unlawful for any person to erect, alter, repair, move, convert or demolish a building or building service equipment in violation of the adopted technical codes. The building official may also suspend or revoke a permit issued in error or based on incorrect information under CBMC 13.01.303, and unpermitted work draws an investigation fee of two to four times the standard permit fee under CBMC 13.01.304 in addition to any other penalty.

Frequently Asked Questions

Do I need a permit to build a storage shed in Council Bluffs?
Not if it is small. CBMC 13.01.301 exempts one-story detached accessory buildings used as tool or storage sheds, playhouses and similar structures as long as the floor area does not exceed one hundred twenty square feet; anything larger needs a building permit.
How long is a Council Bluffs building permit good for before I have to start work?
CBMC 13.01.301 gives you one hundred eighty days from issuance to start construction, and the permit also expires if work is suspended for one hundred eighty days after it begins. The building official may grant one extension of up to one hundred eighty more days.
What happens if I build something in Council Bluffs without getting a permit first?
CBMC 13.01.304 requires an investigation before a permit can be issued after the fact, and adds an investigation fee of two to four times the normal permit fee on top of the permit itself, whether or not a permit is ultimately issued.

Sources & Official References

Other rules in Council Bluffs

All Council Bluffs rules

Compare Council Bluffs to another location·View the Iowa building safety overview

Get notified when Building Permits in Council Bluffs, IA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.