Decatur, AL Building Safety: Building Permits (2026)
Key Facts
- Permit required for
- Excavation, construction, moving, alteration, repair
- Repair exemption
- Repairs of $1,000 or less that keep the structure's character
- Issuance fee
- $10 paper, $5 electronic
- Fee if work starts first
- Two times the scheduled amount
- Permit fee cap
- $200,000 per permitted project
- Issuing officer
- Building inspector of the city
Summary
In the City of Decatur, Alabama, Sec. 25-5 makes it unlawful to begin excavation or construction of any building or structure, including accessory structures, until the building inspector issues a building permit. Repairs of $1,000 or less that do not change the structure's character are exempt, and starting early doubles the permit fee.
It shall be unlawful to commence the excavation for or the construction of any building or other structure, including accessory structures, or to store building materials or erect temporary field offices, or to commence the moving, alteration, or repair (except repairs, not changing the character of the structure and not exceeding one thousand dollars ($1,000.00) in cost, or painting or wallpapering) of any structure, including accessory structures, until the building inspector of the city has issued for such work a building permit including a statement that the plans, specifications and intended use of such structure in all respects conform with the provisions of this chapter. Application for a building permit shall be made to the building inspector of the city on forms provided for that purpose.
Full Breakdown
Sec. 25-5 of the Code of Decatur, Alabama, reaches more than the building itself. Beginning excavation, storing building materials, erecting a temporary field office, or moving, altering, or repairing any structure without a permit is unlawful. The only carve-outs are repairs that do not change the character of the structure and cost no more than $1,000.00, and painting or wallpapering. Applications go to the building inspector on forms the city provides.
Sec. 25-6 requires a plan or plat drawn to scale showing the lot's shape and dimensions, the size and location of each building, existing and intended uses, and the setback and side lines of buildings on adjoining lots. The inspector approves plans only after examining them in detail, and a disapproval must be stated in writing on the application with the cause. A permit never waives any provision of the zoning chapter. Sec. 25-7 adds a certificate of occupancy before any new or altered structure is used.
Fees come from Chapter 7. Sec. 7-7 adds an issuance fee of $10 on paper forms or $5 on electronic applications. Sec. 7-57 charges $15 for the first $1,000 of valuation plus $5 per additional thousand up to $50,000, then steps down to $4, $3, and $2 per thousand in higher bands, with the permit fee capped at $200,000 per project. Work valued at $1,000 or less carries no fee unless an inspection is required, in which case the charge is $15 per inspection. Plan review adds 50 percent under Sec. 7-58. Sec. 7-57.2 adds $1 per $1,000 of construction on nonresidential permits, remitted to the Alabama Building Commission. Sec. 7-5 requires contractors to hold a Decatur business license and register with the building department.
Violations & Fines
Work started before the permit issues costs double: Sec. 7-8 sets the fee at two times the scheduled amount, and Sec. 7-4 doubles the permit fees for any permitted work commenced without the permit. Under Sec. 7-4, each day or portion of a day that a violation continues is a separate offense. Sec. 25-5 itself makes commencing covered work without the building inspector's permit unlawful.
Frequently Asked Questions
Do I need a permit to repair a house in Decatur?
What happens if I start work before getting the permit?
What must I submit with a Decatur building permit application?
How much is the Decatur building permit fee?
Sources & Official References
Other rules in Decatur
Compare Decatur to another location·View the Alabama building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.