Key Facts

Governing section
Sec. 17.04.100, permit issuance license requirement
License required
Valid CA contractor's license plus city business license
Adopted code
2025 California Building Code, Title 24 Part 2
Fee postponement
Residential/nonresidential fees deferrable to final inspection
Nonresidential surcharge
Extra 2% administrative fee if fees postponed
Violation
Misdemeanor under Sec. 17.04.020

Summary

Merced will not issue a building permit for commercial or industrial construction work unless the applicant holds a valid California contractor's license and a city contractor's business license, under Municipal Code Sec. 17.04.100. Doing unpermitted or unlicensed construction work is a misdemeanor under Sec. 17.04.020.

No permit shall be issued to any person to do or cause to be done any construction work on commercial or industrial projects regulated by this chapter, except to a person holding a valid unexpired and unrevoked California contractor's license and city contractor's business license except when and as otherwise provided in this chapter.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 85 - 1-26).

Full Breakdown

Sec. 04, which adopts the 2025 California Building Code, Title 24 Part 2, by reference under Sec. 010 as the operative construction and permitting standard for the city, and makes violating any of its adopted provisions a misdemeanor under Sec. 12 of the Municipal Code. Once a permit issues, Sec. 110 and Sec. 120 let an owner postpone paying the building permit fees tied to a list of code sections, including Secs. 020, until final inspection or issuance of a certificate of occupancy, whichever comes first, provided the owner consents to utility disconnection for breach; nonresidential postponements add a 2 percent administrative surcharge on those fees.

If postponed fees go unpaid for a year after the permit issues, the owner must instead pay whatever fee is in effect at final inspection. All permit fees are ultimately set by city council resolution under Sec. 130.

Violations & Fines

Performing commercial or industrial construction work without a properly licensed contractor, or without the required building permit, is a misdemeanor under Sec. 17.04.020, chargeable under Chapter 1.12 of the Municipal Code. An owner who postpones permit fees under Sec. 17.04.110 or 17.04.120 and then breaches the payment agreement can have the city deny approvals or disconnect utilities, and unpaid postponed fees older than one year are recalculated at the rate in effect at final inspection.

Frequently Asked Questions

Can a homeowner pull their own commercial building permit in Merced?
Sec. 17.04.100 restricts commercial and industrial permits to applicants holding a valid, unexpired California contractor's license and a city contractor's business license, 'except when and as otherwise provided in this chapter.' The section is written around licensed contractors, so a project regulated as commercial or industrial construction needs a licensed contractor of record to obtain the permit.
Can I delay paying Merced's building permit fees?
Yes, on request. Sec. 17.04.110 lets a residential owner postpone the fees listed for specific code sections until final inspection or certificate of occupancy, whichever comes first, as long as the owner agrees the city can deny approvals or disconnect utilities for breach. Sec. 17.04.120 offers the same option for nonresidential projects but adds a 2 percent administrative fee at application.
What happens if I never pay the postponed building permit fee?
If a postponed fee under Sec. 17.04.110 or 17.04.120 remains unpaid one year after the building permit issues, the owner must instead pay whatever fee schedule is in effect at the time of final inspection or certificate of occupancy, not the lower rate that applied when the permit was issued.

Sources & Official References

Other rules in Merced

All Merced rules

California rules heatmap·Compare Merced to another location·View the California building safety overview

Get notified when Building Permits in Merced, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.