Midland, TX Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Code adopted
2018 International Building Code, Appendices B, C, G, N
Contractor bond
$10,000 bond required before permit issuance
Homeowner work
Still needs a permit and must pay fees
Site precondition
Lot must be platted or site-plan approved first
Early clearance permit
90 days residential, 180 days commercial
General penalty
Up to $500/day fine, or $2,000 for fire/zoning

Summary

Midland requires a building permit under Chapter 4-1 of the Code of Ordinances before any construction, alteration, repair or demolition covered by the adopted 2018 International Building Code. The Building Official issues permits only after a contractor posts a $10,000 bond, site conditions are met, and fees from the current Fee Schedule are paid; homeowners doing their own work still need a permit.

The specifications, rules and regulations entitled 2018 International Building Code together with appendices B, C, G and N as promulgated and published by the International Code Council, Inc, are hereby adopted as the Building Code as fully as if copied at length in this Chapter and are hereby incorporated herein by reference and made a part of this Chapter.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Municipal Code: Supplement 1 Update 2).

Full Breakdown

Midland adopts the 2018 International Building Code, with Appendices B, C, G and N, as its Building Code 'as fully as if copied at length' in Sec. 4-1-2, governing any construction, alteration, repair, or demolition of a building or structure inside the city limits (Sec. 4-1-1). Every contractor or builder doing permitted work must post a $10,000 bond approved by the City Attorney before the Building Official may issue a permit (Sec. 8). A homeowner may do the work on his or her own home without hiring a contractor, but that privilege does not excuse the owner from obtaining a permit and paying the required fee, which is set by the City's current adopted Fee Schedule (Sec.

2). Before a permit can be issued for new construction or a substantial addition, the site must satisfy several conditions under Sec. 4-1-4: any required sidewalk must be built or bonded, the lot must be a platted or officially site-plan-approved building site, and a refuse-collection plan must be on file if a dedicated alley is not conveniently located for pickup. The Building Official will not issue a final electrical or gas clearance or a certificate of occupancy until required sidewalks are finished and approved by the Director of Engineering Services.

The City Council may grant a hardship exception or variance from the Sec. 4-1-4 site requirements, and the Planning and Zoning Commission can waive sidewalk construction on cul-de-sacs in one- and two-family zoning districts (Sec. 4-1-5). Builders needing to occupy a new structure before final inspection can apply for an early clearance permit, valid 90 days for residential and 180 days for commercial projects, backed by the same $10,000 bond (Sec. 4-1-8).

Violations & Fines

Building without a required permit, or failing to obtain the $10,000 contractor's bond, exposes the responsible party to the City's general penalty under Sec. 1-3-1: a fine up to $500.00 per offense, with each day a violation continues charged as a separate offense (violations of fire-safety, zoning or health and sanitation ordinances can reach $2,000.00). The Building Official can also issue a stop-work order and revoke the permit for uncontained construction debris under Sec. 4-1-3 (105.8.1), and no final electrical, gas or occupancy clearance will be issued until required sidewalks are completed under Sec. 4-1-4(A).

Frequently Asked Questions

Do I need a permit to build a shed or add onto my own house in Midland?
Yes. Sec. 4-1-3 (amending Building Code § 105.8(c)) lets a homeowner do the work personally for the exclusive benefit of the family, but it expressly does not exempt the owner from obtaining a permit or paying the fee set by the City's current Fee Schedule.
What bond does a contractor need before pulling a building permit?
A contractor or builder must give the City a $10,000 bond approved by the City Attorney, conditioned on complying with the Building Regulations and other City ordinances, before the Building Official will issue a permit (Sec. 4-1-3, adopted Building Code § 105.8(a)).
Can a permit be denied because the lot isn't platted?
Yes. Sec. 4-1-4(C) bars the Building Official from issuing a permit until the tract has been created as a building site, either by a recorded plat approved by the Planning and Zoning Commission or by an officially approved site plan providing the required utility, drainage and street improvements.
What happens if I occupy a new building before it passes final inspection?
Occupying a structure before the Building Official issues a certificate of occupancy is a violation unless the builder obtained an early clearance permit under Sec. 4-1-8, which is valid for 90 days on residential work and 180 days on commercial work and requires the same $10,000 bond.

Sources & Official References

Other rules in Midland

All Midland rules

Texas rules heatmap·Compare Midland to another location·View the Texas building safety overview

Get notified when Building Permits in Midland, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.