Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
2000 International Building Code
Base permit fee
$30 plus $0.15/sq ft
Start-work-early penalty
All fees doubled (Sec. 18-34(d))
Enforcing body
City of Mission Building Division
Extra local standards
Framing, insulation, foundation (18-38 to 18-41)

Summary

Mission requires a building permit before any construction, alteration, or repair. Chapter 18, Article II of the City Code adopts the 2000 International Building Code, and the city's own fee schedule sets a $30 base permit fee that doubles if you start work before the permit issues.

Sec. 18-31. - Adopted. The 2000 International Building Code is hereby adopted in its entirety, exclusive of fee related portions. ... Sec. 18-34(d) Double fee if work started before permit obtained. Where work for which a permit is required by this chapter is started or proceeded with prior to obtaining such permit, the fees in this section shall be doubled, but the payment of such double fee will not relieve any persons from fully complying with the requirements of this chapter in the execution of the work nor from any other penalties prescribed in this section.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 31).

Full Breakdown

The City of Mission's Building Division issues permits under Chapter 18, Article II of the Code of Ordinances, which adopts the 2000 International Building Code (Sec. 18-31) and the 2000 International Residential Code (Sec. 18-32). Section 18-34 sets the fee schedule: a $30 base building-permit fee plus $0.15 per square foot and a $5 technology fee, with commercial plan review at half the permit fee. Start work before pulling the permit and Section 18-34(d) doubles every fee. Mission also layers local framing, insulation, and foundation standards (Secs. 18-38 through 18-41) on top of the IBC, reflecting Rio Grande Valley wind and flood exposure.

Violations & Fines

Building without a required permit doubles all permit fees under Sec. 18-34(d). Violating an adopted code provision is an offense under Sec. 18-37, fined per Sec. 1-14, and a code failure triggers a red-tag stop plus a $35 reinspection fee.

Frequently Asked Questions

Do I need a permit to build in Mission, Texas?
Yes. Chapter 18, Article II adopts the 2000 International Building Code, which requires a permit before construction, and Sec. 18-34 sets permit fees for new work, additions, remodels, and repairs.
What happens if I start construction before getting the permit?
Section 18-34(d) doubles every permit fee when work begins before the permit is obtained. Paying the double fee does not excuse full compliance with the code or other penalties.
What does a building permit cost in Mission?
A $30 base fee plus $0.15 per square foot and a $5 technology fee. Commercial projects add plan review at half the permit fee (Sec. 18-34).

Sources & Official References

Other rules in Mission

All Mission rules

Texas rules heatmap·Compare Mission to another location·View the Texas building safety overview

Get notified when Building Permits in Mission, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Hidalgo County handle building permits.

Edinburg, TX
Some Restrictions
Pharr, TX
Some Restrictions
Mcallen, TX
Some Restrictions