Key Facts

No-permit threshold
$1,000 or less in material and labor (§150.002(B))
Fee basis
ICC valuation tables or contract price, whichever is higher
Plan review discount
10% fee with an approved third-party reviewer
Enforcing official
Building Official, Engineering and Development Services
Appeals body
Construction Board of Adjustments (§150.003)
Maximum penalty
$500 fine or 30 days jail (§150.999)

Summary

In the Town of Mount Pleasant, the Building Official values every project with the ICC Building Valuation Tables or the contractor's price, whichever is higher, then sets the permit fee under the Engineering and Development Services fee schedule. Projects where material and labor together run $1,000 or less need no permit, unless the Building Official requires an inspection.

(A) Valuation for new construction. Building valuation for new construction will be determined by the Building Official, based on the most current Building Valuation Tables, as published by International Code Council (ICC) or contract amount, whichever is higher. Upon determination of valuation, the Building Official will set the amount of the permit fee pursuant to the latest Department of Engineering and Development Services fee schedule. All building permits are value-based permits. (B) Where valuation (material and labor) does not exceed $1,000. No permit is required, unless an inspection is required. (C) Work started without permit. Where work for which a permit is required by the code is started or proceeded with prior to obtaining the permit, per the latest Department of Engineering and Development Services fee schedule, but the payment shall not relieve any persons from fully complying with the requirements of the code in the execution of the work, nor from any other penalties prescribed herein.

Full Breakdown

001 adopts the International Building Code, International Residential Code, International Plumbing, Mechanical and Fuel Gas Codes, the National Electrical Code, the International Property Maintenance Code, the International Existing Building Code and the South Carolina Fire Code, each as amended by the South Carolina Building Codes Council, plus the town's own flood damage prevention rules in Chapter 152. 002 sets how the Building Official prices a permit: valuation comes from the ICC Building Valuation Tables or the signed contract amount, whichever is higher, and every building permit in the Town of Mount Pleasant is value-based.

Work valued at $1,000 or less in combined material and labor needs no permit unless the Building Official calls for an inspection. A structural plan review adds its own fee once valuation tops $1,000, due at submittal and non-refundable once review starts; using a town-approved third-party reviewer cuts that plan review fee to 10% of the standard amount. 002(C). 003 hears appeals from the Building Official's decisions and can vary a technical code requirement, but never the Board-of-Appeals sections the town excluded when it adopted each ICC code. 100.

Violations & Fines

Proceeding with work that needed a permit before obtaining one does not relieve the contractor of code compliance or of any other penalty, per § 150.002(C). Whoever violates Chapter 150 where no other penalty is set faces a fine up to $500, up to 30 days imprisonment, or both under § 150.999, with each day a separate offense capped at whatever a similar state offense carries. Occupying a building before its certificate of occupancy issues is a separate misdemeanor under § 150.100.

Frequently Asked Questions

Do I need a permit for a small repair in Mount Pleasant?
Not if the combined material and labor cost is $1,000 or less. Section 150.002(B) of the Mount Pleasant Code of Ordinances waives the permit in that case, unless the Building Official decides the work still needs an inspection, in which case a permit is required regardless of cost.
How does the Town calculate my building permit fee?
The Building Official prices the permit from the ICC Building Valuation Tables or your signed contract amount, whichever is higher, under § 150.002(A). All Mount Pleasant building permits are value-based, and a separate plan review fee applies once the valuation passes $1,000 and a structural review is required.
What happens if I start construction before my permit is issued?
You still have to pay the permit fee and fully comply with the adopted building codes. Section 150.002(C) makes clear that starting early does not excuse you from the code or from any other penalty the town imposes, including the fine under § 150.999.
Who hears an appeal of the Building Official's decision?
The Construction Board of Adjustments, created by § 150.003, hears appeals and can vary a technical building, fire, or flood code requirement when at least three members agree, though it cannot decide new Board-of-Appeals matters the town excluded from the adopted ICC codes.

Sources & Official References

Other rules in Mount Pleasant

All Mount Pleasant rules

Compare Mount Pleasant to another location·View the South Carolina building safety overview

Get notified when Building Permits in Mount Pleasant, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Charleston County handle building permits.

Charleston, SC
Some Restrictions
North Charleston, SC
Some Restrictions