Key Facts

Governing section
SCC 30.50.406
Application form
Written, filed with building official
Fee timing
Due before permit is valid
Permit expiration
18 months after issuance
Extension allowed
One, up to 18 more months
Work-before-permit penalty
Investigation penalty, SCC 30.86.400(9)
Issuing department
Planning and Development Services

Summary

Any owner who intends to build, enlarge, alter, repair, move, demolish, or change the occupancy of a structure in unincorporated Snohomish County must first apply to the building official and obtain a permit before work starts. Gas, mechanical, and plumbing system changes trigger the same requirement.

City-specific rules exist: Marysville, Edmonds, Lynnwood, and Everett have their own building permits rules that differ from Snohomish County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

Any owner or owner's authorized agent who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any gas, mechanical or plumbing system, the installation of which is regulated by this code, or to cause any such work to be performed, shall first make application to the building official and obtain the required permit.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through legislation passed August 12, 2026).

Full Breakdown

406 sets the trigger for residential work: any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building, or to install, alter, remove, convert or replace a gas, mechanical or plumbing system regulated by the code, must first make application to the building official and obtain the required permit before doing or causing that work. 102. 144). 103 exempts specific categories of minor work, such as one-story detached accessory structures under 200 square feet in an urban growth area, sidewalks, driveways, and painting or similar finish work, though flood hazard or critical area rules can still apply to exempt work. 400(9), on top of the standard permit fees.

Violations & Fines

Beginning construction, alteration, or system work before the permit is issued draws an investigation penalty under SCC 30.86.400(9) in addition to the regular permit fee (SCC 30.50.162). The building official can also suspend or revoke an issued permit under SCC 30.85.300 or 30.85.310 (SCC 30.50.146), and a permit never authorizes work that otherwise violates the construction codes or another county ordinance (SCC 30.50.142).

Frequently Asked Questions

Do I need a permit to remodel or repair my house in unincorporated Snohomish County?
Yes. SCC 30.50.406 requires any owner who intends to construct, enlarge, alter, repair, move, or demolish a building, or to alter a gas, mechanical, or plumbing system, to first apply to the building official and obtain the permit before the work begins.
How long is a Snohomish County building permit good for?
SCC 30.50.144 sets every issued permit to expire 18 months after issuance. The building official may grant one written extension of up to 18 additional months if you request it before expiration and show justifiable cause.
What happens if I start work before my permit is issued?
SCC 30.50.162 makes anyone who commences permit-regulated work before obtaining the permit subject to an investigation penalty under SCC 30.86.400(9), charged on top of the standard permit fee the project already owes.
Is any home project exempt from a building permit?
Yes, SCC 30.50.103 lists exemptions such as small detached accessory structures, sidewalks, driveways, and finish work like painting or tiling, but exempt work can still need a separate permit if it sits in a flood hazard or critical area.

Sources & Official References

Other rules in Snohomish County

All Snohomish County rules

Compare Snohomish County to another location·View the Washington building safety overview

Get notified when Building Permits in Snohomish County, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Cities Across Snohomish County