Edmonds, WA Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing rule
Permit required unless IBC §105.2 exemption applies
Exempt sheds
Up to 120 sq ft, 30-inch max eave
Exempt fences
Up to 6 feet high
Permit term
Expires 2 years after issuance
Extension
One 3rd year at 1/4 original fee
Violation
Misdemeanor, separate offense per day

Summary

Edmonds requires a building permit for construction, alteration, repair, demolition or moving of any structure unless the work falls within the city's amended IBC exemption list. A separate demolition permit and performance bond are required before any structure is torn down, and an applicant's rights vest only once a fully complete application is filed.

G. Section 105.2, Work Exempt From Permit, is replaced as follows:Exemptions from permit requirements of this code shall not be deemed to grant authorization for any work to be done in any manner in violation of the provisions of this code or any other laws or ordinances of this jurisdiction. It is the applicant’s responsibility to comply with bulk zoning code standards per ECDC Title 16 and storm water management provisions per Chapter 18.30 ECDC. Permit exemptions shall not apply to work that is not entirely within a building when located in areas of flood hazard or areas within the designated Wildland Urban Interface. Permits shall not be required for the following unless required by the provisions of ECDC Title 23 or Chapter 19.10 ECDC:

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 4444, passed August 3, 2026).

Full Breakdown

10. 025(E) requires a demolition permit and a performance bond or frozen fund that the building official will not release until abandoned septic tanks are capped, foundations knocked down and hauled, right-of-way debris cleared within 30 days, damaged public property restored, and grading returned to original topography. 074 only when a fully complete application, executed by the property owner or authorized agent and accompanied by all required intake and plan review fees, is on file; minor revisions during review do not defeat that completeness. 5, the building official may grant one six-month extension during a declared emergency, and an applicant may request a third and final year at one-quarter the original permit fee, capping any permit's total life at three years before it becomes void and a new permit with full fees is required.

Violations & Fines

Building without a required permit, or working contrary to any adopted building code provision, is a misdemeanor under ECDC 19.85.000, with each day the violation continues treated as a separate offense punishable under ECC 5.50.020. The building official may also pursue code compliance remedies under Chapter 20.110 ECDC alongside criminal penalties, and issuing notices or stop-work orders under amended Section 104.3.

Frequently Asked Questions

What building work is exempt from a permit in Edmonds?
IBC Section 105.2 as amended exempts limited categories such as sheds and playhouses up to 120 square feet with a 30-inch maximum eave, fences up to six feet, retaining walls up to four feet unless they support a surcharge, and sidewalks or driveways no more than 30 inches above grade, but every exemption still has to comply with zoning and stormwater rules.
How long is an Edmonds building permit valid?
Two years from issuance under amended IBC Section 105.5. The applicant can request one extension into a third and final year by paying one-quarter of the original permit fee, but no permit can run longer than three years total before it becomes void and requires a brand-new application and full fees.
When do my rights vest under an Edmonds building permit application?
Under amended IBC Section 105.3.3, rights vest under RCW 19.27.031 and 19.27.074 only once a fully complete application is filed: every required document submitted, professional stamps or certifications provided where needed, and all intake and plan review fees paid, not merely upon initial submission.
What happens if I build without a permit in Edmonds?
It is a misdemeanor under ECDC 19.85.000, with each day the unpermitted condition continues counted as a separate offense punishable under ECC 5.50.020, and the building official can also pursue code compliance action under Chapter 20.110 ECDC.

Sources & Official References

Other rules in Edmonds

All Edmonds rules

Compare Edmonds to another location·View the Washington building safety overview

Get notified when Building Permits in Edmonds, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Snohomish County handle building permits.

Marysville, WA
Some Restrictions
Lynnwood, WA
Some Restrictions
Everett, WA
Some Restrictions