Key Facts

Program basis
Green building incentives under ECDC Title 16
Benefit
Expedited plan review
Proof required
Certification before certificate of occupancy
Expedited review bond
50% of building permit fee
Land use incentive bond
5% of project valuation
Bond term
Two years
If uncertified
Bond surrendered to city as penalty

Summary

Edmonds does not mandate green construction, but projects certifying under the Title 16 green building incentive program get expedited plan review from the planning and development department, backed by a two-year performance bond the city keeps if certification is never actually achieved.

Projects qualifying for green building incentives as allowed in ECDC Title 16 shall be eligible for expedited plan review as administered by the planning and development department. A. Enforcement. Projects participating in the green building incentives program will require proof of certification prior to issuance of certificate of occupancy. B. Failure to achieve certification will require posting a two-year performance bond in favor of the city. Bond amounts will be based on the following: 1. Expedited permit review bond valued at 50 percent of the building permit fee. 2. Land use incentive bond valued at five percent of the project valuation. C. Bonds shall be released upon approval of certification. In the event where certification is not achieved within two years, the bond will be surrendered to the city as a penalty.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 4444, passed August 3, 2026).

Full Breakdown

050 makes projects qualifying for green building incentives under ECDC Title 16 eligible for expedited plan review administered by the planning and development department, but proof of certification must be produced before the city will issue a certificate of occupancy. If certification is not achieved, the applicant must post a two-year performance bond in the city's favor: the expedited permit review bond is set at 50 percent of the building permit fee, and a separate land use incentive bond is set at five percent of the project's valuation.

The bonds are released once certification is approved, but if certification is still not achieved within the two-year window, the full bond amount is surrendered to the city as a penalty rather than returned to the applicant. Proceeds are not treated the same way: the expedited permit review bond becomes permit fee revenue for the city, while the land use incentive bond is directed into the city's general fund. Because the program is opt-in, a developer who never applies for the green building incentive faces no such bonding obligation and simply proceeds through ordinary plan review timelines and fees under the rest of Title 19.

Violations & Fines

Failing to achieve the promised certification within two years does not undo the permit itself, but it forfeits the entire bond: the expedited review bond and the land use incentive bond are both surrendered to the city as a penalty under ECDC 19.00.050(C), with the funds routed to permit fee revenue and the general fund respectively rather than refunded to the applicant.

Frequently Asked Questions

What is Edmonds's green building incentive program?
Under ECDC 19.00.050, projects that qualify for green building incentives allowed in ECDC Title 16 get expedited plan review from the planning and development department, in exchange for posting bonds that guarantee the promised certification is actually completed within two years.
How large is the bond required for Edmonds's green building incentive program?
Two separate bonds apply: an expedited permit review bond valued at 50 percent of the building permit fee, and a land use incentive bond valued at 5 percent of the total project valuation, both held by the city for a two-year certification period.
What happens if a project doesn't achieve green certification in Edmonds?
The performance bond is surrendered to the city as a penalty under ECDC 19.00.050(C); the expedited review bond funds are processed as ordinary permit fee revenue while the land use incentive bond funds go into the city's general fund.

Sources & Official References

Other rules in Edmonds

All Edmonds rules

Compare Edmonds to another location·View the Washington building safety overview

Get notified when Green Building Code in Edmonds, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.