Skip to main content
CityRuleLookup

Lynnwood, WA Building Safety: Green Building Code (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Green standard
LEED Silver (USGBC)
Governing section
LMC 3.82.060(D)(7)
Applies to
MFTE projects, city center subarea only
Minimum project size
50 new units (or 20 added)
Exemption length
8 or 12 years
Review timeline
90 days by director
Noncompliance result
Exemption canceled, back taxes owed

Summary

Lynnwood does not impose a general green building code, but LMC 3.82.060(D)(7) requires any multifamily project seeking the city's property tax exemption in the designated city center residential targeted area to be designed to meet the LEED Silver Standard set by the U.S. Green Building Council, as a condition of the incentive, not of building permit issuance.

D. Project Eligibility. A proposed project must meet the following requirements for consideration for a property tax exemption: ... 7. Leed. The project shall be designed to meet the LEED™ Silver Standard as established by the U.S. Green Building Council (USGBC).

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 3512, passed May 26, 2026).

Full Breakdown

14 RCW within Lynnwood's designated 'residential targeted area,' the city center subarea. S. 100, not as an amendment to the state-adopted building code that governs ordinary construction citywide. A project must also meet a minimum size (at least 50 new units, or 20 added to an existing building), avoid displacing existing tenants, and comply with the underlying building, housing and zoning codes in effect when the application is filed. 120, triggering back taxes, interest and penalties imposed by the Snohomish County assessor under state law.

Violations & Fines

There is no separate criminal penalty for missing the LEED Silver Standard; noncompliance is enforced through the tax exemption contract itself. Under LMC 3.82.120, if the director finds a project no longer meets Chapter 3.82's requirements, including the LEED condition set in LMC 3.82.060(D)(7), the exemption is canceled and the Snohomish County assessor imposes additional property taxes, interest and penalties under state law, with a priority lien available against the land.

Frequently Asked Questions

Does Lynnwood require LEED certification for all new buildings?
No. Lynnwood has no citywide green building code. LEED Silver is required only under LMC 3.82.060(D)(7) for multifamily developers who apply for the city's limited property tax exemption in the designated city center residential targeted area, not for ordinary building permits elsewhere in the city.
What is the LEED Silver requirement tied to?
It is one of the project eligibility conditions in LMC 3.82.060(D) for the Chapter 84.14 RCW multifamily property tax exemption program. A qualifying project must be designed to meet the LEED Silver Standard set by the U.S. Green Building Council before the city will issue a final certificate of tax exemption.
What happens if a tax-exempt project does not deliver LEED Silver?
Under LMC 3.82.120, the director can cancel the property tax exemption for noncompliance with any Chapter 3.82 requirement, including the LEED condition. Cancellation triggers additional taxes, interest and penalties imposed by the Snohomish County assessor, and the city may place a priority lien on the property.

Sources & Official References

Other rules in Lynnwood

All Lynnwood rules

Compare Lynnwood to another location·View the Washington building safety overview

Get notified when Green Building Code in Lynnwood, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Green Building Code in Nearby Cities

How other cities in Snohomish County handle green building code.

Everett, WA
Light Restrictions
Edmonds, WA
Some Restrictions