Orlando, FL Building Safety: Building Permits (2026)
Key Facts
- Adopted code
- Florida Building Code, Eighth Edition (2023)
- Permit extension cap
- 8 extensions max, 90 days each
- Permit transfer
- Requires notarized owner request + fee
- Substantial-improvement trigger
- Alterations over 50% of assessed value
- Local citation
- City Code §§ 13.1, 13.2, 14.03
Summary
Orlando enforces the Florida Building Code, Eighth Edition (2023), for renovation and construction permits, with local amendments capping permit extensions at eight renewals of 90 days each. City Code § 13.2 also sets the rules for transferring a permit to a new owner and for refunding fees on a cancelled project.
105.4.1.4 The fee for renewal, reissuance, or extension of a permit shall be set forth by the administrative authority. The building official may extend a permit no more than eight times and each extension may not exceed 90 days. The building official may require extension applicants to make their request on a form provided for such purpose... 105.4.1.5 Permit transfer. A permit may be transferred from one holder to another, and such transfer may occur before or after work has commenced. The building official shall transfer a permit upon receipt of a written, signed, and notarized request to do so from the owner of the real property to which the permit applies, and the payment of a fee set by resolution of Council and equal to the reasonably estimated administrative cost of transferring a permit.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 92).
Full Breakdown
1 adopts the Florida Building Code, Eighth Edition (2023) as the 'Orlando Building Code,' governing all permitted construction, alteration, and renovation work citywide. 2 layers local administrative amendments onto that code's permit provisions. 04(1). 12 makes unsafe or unsanitary structures, including their plumbing, electrical, gas, and mechanical systems, unlawful and subject to abatement by repair or demolition ordered by the building official. 4 caps how many times a renovation permit can be extended: the building official 'may extend a permit no more than eight times and each extension may not exceed 90 days,' with a fee set by Council resolution for each renewal.
5 lets a permit be transferred from one holder to another, before or after work has started, once the building official receives a written, signed, and notarized transfer request from the property owner and payment of the transfer fee. 6 allows the building official to refund permit fees if the permit has not expired, the renovation project is cancelled, and no work has begun, subject to a fee covering the City's administrative cost of processing the refund. 03(A)-(C) of the Property Maintenance Code requires that when alterations or repairs within any 12-month span exceed 50 percent of a building's assessed physical value, the entire building must be brought up to current Florida Building Code new-construction standards, with a 25-50 percent threshold triggering upgrades only to the portions being altered.
Violations & Fines
Undertaking renovation work without an active permit, or work exceeding the scope of an issued permit, is enforced by the building official under the Florida Building Code as locally amended and prosecuted under the Orlando City Code's general penalty provisions. A permit that has been extended beyond the eight-extension, 90-day-per-extension limit in § 13.2(c) lapses, requiring a new application before work can lawfully continue.
Frequently Asked Questions
How many times can I extend an Orlando building permit?
Can I transfer my renovation permit to a new owner?
If I cancel my renovation, can I get the permit fee back?
Sources & Official References
Other rules in Orlando
Florida rules heatmap·Compare Orlando to another location·View the Florida building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.