Key Facts

Permit trigger
New construction, additions, alterations, repairs, demolition
Residential fee
1% of contract price + 4% surcharge, $52 min
Commercial fee
1.2% of contract price + 4% surcharge, $104 min
No-permit penalty
Triple the ordinary permit fee
Governing code
Massachusetts State Building Code (since 1975)

Summary

Taunton requires a permit before any construction, addition, alteration, repair, demolition or foundation work covered by City Code Sections 250-2 through 250-6. Residential building permits cost 1% of the contract price plus a 4% surcharge, with a $52 minimum, and doing the work without a permit first triples the fee.

No person shall undertake, authorize, allow, or cause any work referenced in §§ 250-2 through 250-6, inclusive, to be done without first applying for and obtaining permits therefor. ... Use or Application Type of Permit Description Fee ... Residential Building All new construction, additions, alterations, repairs, demolition, foundations and permanent structures 1% of contract price plus 4% of permit fee (or $0.40 per square foot plus 4% of permit fee) ($52 minimum) ... Commercial Building Work performed without a permit Triple fee

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4508986; v12 updated 2025-09-22; through 09-22-2025).

Full Breakdown

Since Massachusetts' new State Building Code took effect January 1, 1975 under Section 208-1, it superseded Taunton's own building code, so construction in the City is governed by the state code with local permit fees set in Chapter 250, Article I. Section 250-1 states plainly that no person may undertake, authorize, allow or cause any work covered by Sections 250-2 through 250-6 without first applying for and obtaining the appropriate permit, and Section 250-2 sets the building permit fee schedule the Building Department charges. 50 per square foot plus 4%, with a $104 minimum.

Separate line items apply to a certificate of occupancy ($104 per unit commercial), temporary structures, tents and awnings, solar panels and wind generators, and permit replacement ($26). Work performed without first obtaining the permit is billed at triple the ordinary fee under both Section 250-2 and the general penalty at Section 250-7, and the Building Commissioner may also seek an injunction against the violator in addition to that fine.

Violations & Fines

Doing covered work before obtaining the permit triggers a fee three times the amount that would otherwise apply, under Section 250-2's 'work performed without a permit' line and the general penalty at Section 250-7. Section 250-7 also lets the Building Commissioner, at his sole discretion, seek injunctive relief in court against anyone who builds, alters or demolishes without the required permit, on top of the tripled fee already owed.

Frequently Asked Questions

What work requires a building permit in Taunton?
Section 250-1 covers any work listed in Sections 250-2 through 250-6: new construction, additions, alterations, repairs, demolition, foundations and permanent structures, along with electrical, plumbing, gas and sheet metal work. You must apply for and get the permit before starting; the section is explicit that undertaking, authorizing or causing that work without a permit first is prohibited.
How much does a residential building permit cost in Taunton?
Under Section 250-2, residential new construction, additions, alterations, repairs, demolition, foundations and permanent structures cost 1% of the contract price plus a 4% permit surcharge, or $0.40 per square foot plus the 4% surcharge, whichever method applies, subject to a $52 minimum fee.
What if I build first and get the permit later in Taunton?
You pay triple the fee. Section 250-2 lists 'work performed without a permit' as its own line item billed at triple the standard rate, and Section 250-7 backs that up with a matching general penalty plus the option for the Building Commissioner to seek an injunction against you in court.

Sources & Official References

Other rules in Taunton

All Taunton rules

Compare Taunton to another location·View the Massachusetts building safety overview

Get notified when Building Permits in Taunton, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in Bristol County handle building permits.

Fall River, MA
Some Restrictions
New Bedford, MA
Some Restrictions