Key Facts
- Permit required for
- Erecting, enlarging or structurally altering any building or structure
- Issuing official
- Construction Official
- Filing format
- Application and scaled plans in duplicate
- Appeal of denial
- Written notice within five days to Board of Adjustment
- Board of Adjustment decision window
- Within 30 days
- Code section
- § 414-41
Summary
In the Town of West New York, New Jersey, no building or structure in any district can be erected, enlarged or structurally altered without a building permit issued by the Construction Official. The application and scaled plans must be filed in duplicate with a survey. A denial can be appealed to the Board of Adjustment within five days.
A. No building or structure in any district shall be erected, enlarged or structurally altered without a building permit, duly issued, upon application, by the Construction Official. No permit shall be issued except in conformity with this chapter unless approved by the Planning Board or the Board of Adjustment. ... B. All applications for building permits and supporting documentation shall be made in duplicate and accompanied by plans in duplicate, drawn to scale, showing the following: (1) An accurate survey, at the scale of the town's Tax Maps, showing shape, dimensions, radii, angles and area of the lot on which the building is proposed to be erected or of the lot on which it is situated if an existing building. (2) The block and lot numbers as they appear on the official Town of West New York's Tax Map.
Full Breakdown
Section 414-41 of the Town Code, in Chapter 414 Zoning, is the building permit requirement of the Town of West New York. Subsection A says no building or structure in any district shall be erected, enlarged or structurally altered without a building permit, duly issued, upon application, by the Construction Official. No permit is issued except in conformity with the zoning chapter unless approved by the Planning Board or the Board of Adjustment. The subsection was amended 6-19-1996 by Ord. No. 26/96.
Subsection B sets the filing package. Applications and supporting documentation must be made in duplicate and accompanied by plans in duplicate, drawn to scale. The plans must show an accurate survey at the scale of the Town Tax Maps, with the shape, dimensions, radii, angles and area of the lot, plus the block and lot numbers from the official Town Tax Map. They must also show the exact size and location of the proposed building or alteration and of the other buildings on the lot, the dimensions of all yards, the existing and intended use and number of dwelling units, any topographic information needed to confirm conformity, and the locations, widths and grades of driveways serving parking areas.
The Construction Official issues the permit when the use, plans and application conform to the chapter and all other reviews are complete (§ 414-44A). Permits are issued in duplicate, and one copy stays conspicuously displayed on the premises while construction work is performed (§ 414-44B). Permits are issued separately for each application, and only if adequate water and sanitary sewers are available (§ 414-46).
A denial is sent in writing with the grounds. The applicant has five days to notify the Construction Official of an appeal, and the Board of Adjustment must review and affirm or reverse within 30 days on five days' written notice (§ 414-45). The Official can revoke a permit for false or misleading applications under § 414-47.
Violations & Fines
Section 414-44B bars any owner, contractor, workman or other person from performing building operations without a displayed building permit, or after notification that the permit has been revoked. Under § 414-40B the Construction Official gives written notice of a violation of the zoning chapter and orders the corrective action. Under § 414-47 a permit based on a false or misleading application can be revoked, and an indemnity bond can be required before a new permit.
Frequently Asked Questions
When is a building permit required in West New York?
What must I file with a building permit application?
What if the Town denies my building permit?
Do I have to post the permit at the job site?
Sources & Official References
Other rules in West New York
Compare West New York to another location·View the New Jersey building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Permits in Nearby Cities
How other cities in this county handle building permits.