Key Facts

Adopted electrical code
National Electric Code + WAC 296-46B
Permit required
Before any electrical installation/alteration/repair
Minor-work exemption
$1,500 IRC exemption excludes electrical
Civil penalty
$100-$2,050 per violation
Criminal penalty
Gross misdemeanor, up to $5,000/364 days
Appeal deadline
14 days to Hearing Examiner
Enforcing agency
Bellingham Building Division

Summary

Bellingham requires a Building Division permit before any installation, alteration, repair or replacement of an electric system, applying the National Electric Code and Chapter 296-46B WAC under Construction Administrative Code Section 101.5.7. The city's minor-alteration exemption for small home repairs does not cover electrical work, and violations draw civil infractions or criminal charges.

101.5.7 Electrical. The provisions of the National Electric Code (NEC) and Chapter 296-46B WAC shall apply to the installation, alteration, repair or replacement of electric systems that are within the scoping provisions of the NEC. ... 105.1 Required. Any owner or authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by this code, or to cause any such work to be done, shall first make application to the Building Official and obtain the required permits.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 2026-06-015, passed June 1, 2026).

Full Breakdown

020. 7 applies the National Electric Code and Chapter 296-46B WAC to the installation, alteration, repair or replacement of any electric system within the NEC's scoping provisions. 1 requires the owner or authorized agent to apply for and obtain a permit before starting that work, and bars commencing work until the permit is issued. 2, includes a narrow carve-out for alterations to IRC dwellings costing $1,500 or less in a six-month period, but that exemption explicitly says it does not apply to electric, plumbing or mechanical devices, so essentially all electrical installation work still needs its own permit regardless of cost.

1 lets the applicant submit the permit application the next business day rather than beforehand. 1; approval of one stage never authorizes a code violation elsewhere. 1, though the Examiner cannot waive code requirements.

Violations & Fines

Unpermitted or noncompliant electrical work is a civil infraction of $100 to $2,050 per violation under Section 114.4, with each day of continued violation a separate offense, issued by the Building Official or a Designated Official and heard in Bellingham Municipal Court under RCW Chapter 7.80. A person who intentionally, knowingly, recklessly or with criminal negligence violates the electrical code commits a gross misdemeanor, punishable by up to $5,000 in fines (minimum $250) and up to 364 days in jail.

Frequently Asked Questions

Do I need a permit for minor electrical work in Bellingham?
Yes. Bellingham's $1,500 minor-alteration exemption for one- and two-family dwellings under Construction Administrative Code Section 105.2, item 19, does not apply to electrical devices, so virtually any electrical installation, alteration, repair or replacement still needs a Building Division permit before work starts.
What code governs electrical work in Bellingham?
Construction Administrative Code Section 101.5.7 applies the National Electric Code and Chapter 296-46B WAC to any installation, alteration, repair or replacement of an electric system within the NEC's scoping provisions, as adopted by the city at BMC 17.10.020.
What happens if I do electrical work without a permit in Bellingham?
The Building Official can issue a notice of violation and, if it isn't corrected, a civil infraction of $100 to $2,050 under Section 114.4, with each day of continued unpermitted work counted as a separate offense; intentional or reckless violations can be charged as a gross misdemeanor.
Can I appeal a Bellingham Building Official's electrical permit decision?
Yes. Construction Administrative Code Section 113.1 gives you 14 days from the order or determination to appeal to the City of Bellingham Hearing Examiner, though the Examiner has no authority to waive any requirement of the code.

Sources & Official References

Other rules in Bellingham

All Bellingham rules

Compare Bellingham to another location·View the Washington building safety overview

Get notified when Electrical Permits in Bellingham, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.