Key Facts

Adopted electrical code
National Electrical Code, 2005 Edition
Governing section
Code of Ordinances § 10-2, § 10-3
Permit issuer
Director of public works or designee
Enforcement authority
Building official, via parish attorney injunction
Applies to
Unincorporated Caddo Parish only

Summary

Caddo Parish adopts the 2005 National Electrical Code for unincorporated areas and requires a permit from the director of public works before any electrical system is installed, altered or replaced. No electrical work may be occupied or used until a state-approved inspector certifies compliance.

City-specific rules exist: Shreveport has its own electrical permits rules that differ from Caddo Parish's county-level regulations. If you live in Shreveport, check the city-specific page instead.

Pursuant to R.S. 40:1730.21 et seq., the following codes are hereby adopted as the regulations governing the construction of buildings and other structures in the parish... The International Building Code, 2006 Edition... not including Chapter 1—Administration, Chapter 11—Accessibility, Chapter 27—Electrical, and Chapter 29—Plumbing Systems... National Electrical Code, 2005 Edition, as published by the National Fire Protection Association.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 26 | Unified Development Code: Supplement 2).

Full Breakdown

Section 10-2 of the Code of Ordinances, adopted pursuant to R.S. 40:1730.21 et seq., adopts the National Electrical Code, 2005 Edition, as published by the National Fire Protection Association, as the governing electrical standard for construction in the parish outside incorporated municipalities. The 2006 International Building Code and International Residential Code are adopted for structural work, but both explicitly exclude their own electrical chapters and parts, leaving the 2005 NEC as the sole electrical standard. Section 10-3 makes it unlawful to erect, install, enlarge, alter, repair, remove, convert or replace any electrical system regulated by these adopted codes without first obtaining a permit from the director of public works or his designee.

Section 10-4 requires the permit application to identify the owner, all contractors, the construction location, a description of the work including whether it involves electrical work, and a sworn certification that the work will comply with applicable codes. Section 10-5 bars occupying or using any permitted structure before the owner files a certificate of completion and compliance made by a state-approved building inspector. Section 10-1 assigns enforcement outside incorporated areas to the parish's appointed building official, and section 10-6 lets the building official go through the parish attorney to enjoin unpermitted construction or the occupancy of noncompliant work.

Violations & Fines

Doing electrical work without a permit, or occupying a structure before certification, is unlawful under sections 10-3 and 10-5; the building official may seek an injunction under section 10-6 through the parish attorney to halt the work or occupancy, in addition to any penalty under the Code's general enforcement provisions.

Frequently Asked Questions

What electrical code does Caddo Parish enforce?
Section 10-2 adopts the National Electrical Code, 2005 Edition, as published by the National Fire Protection Association, as the governing standard for the unincorporated parish. The adopted 2006 IBC and IRC both exclude their own electrical chapters, leaving the 2005 NEC controlling.
Do I need a permit for electrical work in unincorporated Caddo Parish?
Yes. Section 10-3 makes it unlawful to erect, install, enlarge, alter, repair, remove, convert or replace any electrical system regulated by the adopted codes without a permit from the director of public works or his designee.
Can I use a new electrical system before it's inspected?
No. Section 10-5 prohibits occupying or using any permitted structure or system before the owner files a certificate of completion and compliance made by a state-approved building inspector.

Sources & Official References

Other rules in Caddo Parish

All Caddo Parish rules

Compare Caddo Parish to another location·View the Louisiana building safety overview

Get notified when Electrical Permits in Caddo Parish, LA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Cities Across Caddo Parish