Key Facts
- Adopted code
- 2017 National Electrical Code
- Service disconnect
- Within 30 feet of the structure served
- Applies to
- All structures with electricity, manufactured homes included
- Fee schedule
- Set by resolution of the county commission
- Travel fees
- $20 zone 1, $40 zone 2, $60 zone 3
- Maximum penalty
- $500 fine or six months, or both
Summary
Unincorporated Elko County, Nevada builds to the 2017 National Electrical Code under Elko County Code § 3-1-1(D). A county amendment requires the exterior service disconnect within 30 feet of the structure it serves, manufactured homes included, and electrical permit fees are set by resolution.
In all construction hereafter to be made within Elko County, the same shall be in accordance with what is now known as the International Codes (I-codes), as published by the International Code Council, the Uniform Codes, as published by the International Association of Plumbing and Mechanical Officials. The following codes are hereby adopted as a revision to this chapter: ... (D) The 2017 National Electrical Code (NEC), standard for electrical wiring and apparatus as recommended by the National Fire Protection Association, hereinafter referred to as the electrical code. ... (D) Service Equipment - Electrical Disconnecting Means: The 2002 national electrical code (NEC), article 230 - VI, section 230.70 (A) (1) shall be amended as followed for the protection of emergency service personnel: An exterior service disconnecting means shall be located within 30 feet of the structure it serves for all structures with electricity including manufactured homes.
Full Breakdown
The Elko County Board of County Commissioners adopts the electrical code in Title 3, Chapter 1. Section 3-1-1(D) adopts the 2017 National Electrical Code, the standard for electrical wiring and apparatus recommended by the National Fire Protection Association, and defines it as the electrical code. Subsection (A) of the same section folds the administration chapter of the NEC into the county's administrative code, excluding fee schedules adopted by resolution. Section 3-1-4(D) then amends article 230, section 230.70(A)(1), for the protection of emergency service personnel: an exterior service disconnecting means must be located within 30 feet of the structure it serves, for all structures with electricity including manufactured homes.
Fees follow a separate track. Section 3-1-5(D) amends Table K112, Electrical Permit Fees, and states that the system fee schedule, which does not include the permit issuing fee, is set by resolution adopted by the Elko County commission. Section 3-1-4(A)(3) says permit fees are set by resolution of the Board of Commissioners, kept at the Community Development office, and adjusted every other year using the western urban consumer price index published in January. A property requiring a permit in travel zones 1, 2 or 3 pays a travel fee, with base fees of $20, $40 and $60 respectively.
Section 3-1-4(E) bars issuing a building permit where a governmental entity or utility provides water or sewer service until evidence of paid connection fees is produced. Under § 3-1-2, later editions of the NEC take effect automatically once the county building official posts notice, unless the commission specifically disapproves the edition within one hundred twenty days of the building official receiving it. Hoop houses and high tunnels carry their own note in § 3-1-4(A)(1)(f): installation of electrical, mechanical and sanitary plumbing is not exempt from permits. Section 3-1-3 reads every reference to a city or municipality in the codes as Elko County.
Violations & Fines
Under § 3-1-7, violating the adopted National Electrical Code, a permit or an approved plan is a misdemeanor punishable by a fine of not more than $500, imprisonment for not more than six months, or both. Each ten days a violation continues is a separate offense when nothing else is specified, and a court can close, seal or impound the premises.
Frequently Asked Questions
Which electrical code does Elko County enforce?
How close must the main disconnect be to the building?
What does an electrical permit cost in unincorporated Elko County?
Is a hoop house wired for power exempt from permits?
Sources & Official References
Other rules in Elko County