Farmersville, TX Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
2023 National Electrical Code
Governing sections
§ 14-118, § 14-124
Unpermitted work penalty
Double the permit fee
Permit scope
Separate permit per unit/business
Enforcing official
City-designated electrical inspector
Interference penalty
Separate offense, § 14-123

Summary

Farmersville has adopted the 2023 National Electrical Code and requires a separate permit for each building unit, storage space, or business needing an electrical inspection. Starting work without paying the permit fee first doubles the fee the property owner owes.

Permit fees. ... Any person granted a permit for electrical installation of conductors or equipment shall pay to the city an inspection fee in such amount as is determined from time to time by city council and set forth in the Master Fee Schedule attached as Appendix A to this Code. ... Separate permits. A separate permit shall be required for each separate building unit, storage space or business, whether such unit is metered separately or conjunctively ... Double fee when work commenced without permit. Any person who shall commence any work for which a permit is required without first having paid the required permit fee shall, if subsequently permitted to pay the permit fee, pay double the permit fee fixed by this section for such work.

Full Breakdown

Farmersville Code of Ordinances § 14-118 adopts the 2023 Edition of the National Electrical Code of the National Fire Protection Association as the city's electrical code, with local amendments from the North Central Texas Council of Governments on file with the city secretary under Section 14-119. Section 14-124 sets the permit mechanics: any person granted a permit for electrical installation of conductors or equipment must pay an inspection fee set in the Master Fee Schedule (Appendix A), and a separate permit is required for each separate building unit, storage space, or business, whether metered separately or conjunctively, except that individual trailer disconnect switches in trailer courts are not treated as a service entrance.

If work begins before the permit fee is paid, Section 14-124(c) doubles the fee owed, unless the electrical inspector is satisfied the work was emergency work that could not practically wait for a permit. Section 14-125 adds that if an inspection finds the installation does not comply with the article, the electrical inspector must notify the installer of the defects, and a reinspection fee applies, set by the Master Fee Schedule. The City Manager or their designee, the electrical inspector, enforces the article, may enter buildings during reasonable hours to inspect wiring, and keeps a full record of all permits and inspections under Section 14-122.

Violations & Fines

Interfering with the electrical inspector while performing official duties is a separate offense under Section 14-123. Commencing electrical work without first paying the required permit fee triggers a doubled fee under Section 14-124(c), and failed inspections carry a reinspection fee under Section 14-125(b), both set by the Master Fee Schedule in Appendix A.

Frequently Asked Questions

What electrical code does Farmersville use?
Section 14-118 adopts the 2023 Edition of the National Electrical Code of the National Fire Protection Association, together with amendments from the North Central Texas Council of Governments, as the city's electrical code, effective under Ord. No. O-2023-1024-001.
Do I need a separate electrical permit for each unit in a building?
Yes. Section 14-124(b) requires a separate permit for each separate building unit, storage space, or business needing electrical work, whether it is metered separately or shares a meter with other units, with a narrow exception for trailer court disconnect switches.
What is the penalty for starting electrical work without a permit in Farmersville?
Section 14-124(c) doubles the permit fee for anyone who commences electrical work before paying the required fee, unless the electrical inspector determines the work was urgent emergency work that could not practically wait for a permit.

Sources & Official References

Other rules in Farmersville

All Farmersville rules

Texas rules heatmap·Compare Farmersville to another location·View the Texas building safety overview

Get notified when Electrical Permits in Farmersville, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Collin County handle electrical permits.

Frisco, TX
Some Restrictions
Plano, TX
Some Restrictions