Fort Collins, CO Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopted code
National Electrical Code, 2023 Edition
Permit required
Before any regulated electrical work begins
Minimum fee
$15, per Table 3-A Building Permit Fees
Appeals
To Building Review Commission, § 5-27(15)
Violation
Civil infraction, § 1-15, per day

Summary

Fort Collins requires a permit before any electrical system covered by the National Electrical Code is installed, enlarged, altered, repaired, or replaced in the city. The 2023 NEC, as locally amended, sets the permit, fee, appeal, and penalty rules the Building Official enforces for wiring and electrical equipment work.

...the City Council has adopted the National Electrical Code, 2023 Edition, as promulgated by the National Fire Protection Association, as amended by the City, which shall have the same force and effect as though set forth in full herein... Section 90.4.1. Permit Required. Any owner, owner's authorized agent or contractor who desires to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical system, the installation of which is regulated by this code, or to cause any such work to be performed, shall first make application to the code official and obtain the required permit for the work.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Municipal Code: Supplement 155 | Transitional Land Use Code (for project before May 17, 2024): Supplement 61 | Traffic Code: Supplement 27).

Full Breakdown

City Code § 5-80 adopts the National Electrical Code, 2023 Edition, as promulgated by the National Fire Protection Association and amended by the City, governing wiring methods and the installation, alteration, and repair of electrical systems. 1, Permit Required: any owner, owner's authorized agent, or contractor who wants to erect, install, enlarge, alter, repair, remove, convert, or replace an electrical system regulated by the code must first apply to the code official and obtain the permit before doing the work. 3, based on the value of the work under 'Table No.

S. 2, following the procedure in § 5-27(15) of the City Code. 1, and electrical signs need that approval before a permit for their installation is granted. '

Violations & Fines

Doing electrical work without the required permit, or otherwise violating the Electrical Code, is a civil infraction under new Section 90.4.4, subject to the penalties in City Code § 1-15. That section caps most civil infractions at a $2,650 fine, with each day of ongoing unpermitted or noncompliant work treated as a separate offense, and the Building Official can withhold related permits until the work is brought into compliance.

Frequently Asked Questions

Do I need a permit for electrical work in Fort Collins?
Yes. Section 90.4.1 of the city's amended National Electrical Code requires any owner, agent, or contractor doing electrical installation, alteration, repair, or replacement work regulated by the code to apply to the code official and obtain a permit before starting the work.
How much does a Fort Collins electrical permit cost?
The fee is based on the value of the work under Table No. 3-A, Building Permit Fees, of the city's Building Code, per Section 90.4.3 of the amended NEC. The minimum fee is fifteen dollars, and the maximum is capped by Colorado Revised Statutes Section 12-115-121.
What happens if I skip the electrical permit?
Unpermitted electrical work is a civil infraction under Section 90.4.4 of the amended NEC, enforced through City Code § 1-15. Penalties can reach $2,650, and each day the violation continues is treated as a new, separate offense until the work is permitted and brought into compliance.
Can I appeal a denied electrical permit?
Yes. Section 90.4.2 lets an applicant appeal a denied application, a refused permit, or a disputed interpretation of the National Electrical Code to the Building Review Commission, following the procedure set out in Section 5-27(15) of the City Code.

Sources & Official References

Other rules in Fort Collins

All Fort Collins rules

Compare Fort Collins to another location·View the Colorado building safety overview

Get notified when Electrical Permits in Fort Collins, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.