Key Facts

Electrical review fee
$60, all uses
Governing rules
675 IAC + ICC IBC, § 150.39
Permit issued by
Building Commissioner
Daily fine
$10-$200 per day
Appeal path
County Commissioners, then State Fire Board

Summary

Hendricks County folds electrical work into its general building permit under Code § 150.40, requiring plans that show the electrical system layout before the Building Commissioner will issue anything. The Planning and Building Department's fee schedule at § 37.25(D) charges a flat $60 to review an electrical permit for any principal or accessory use.

These county ordinances apply to unincorporated areas of Hendricks County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(A) Application for permits. ... Plans and specifications shall include the foundation, basement, floor, roof, wall cross-section, and layouts of the electrical, plumbing, heating, ventilating, and air conditioning systems. ... (B) Permit required. A permit shall be obtained before beginning construction, alteration, repair, or placement of any building or structure, as required by the Zoning Ordinance of the county. All permits shall be issued by the Building Commissioner, and all fees provided for herein shall be paid to the County Planning and Building Department.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2025 S-3: Supplement contains: Local legislation current through Ord. 2024-50, passed 12-10-2024; and State law current through Indiana Legislative Service, 2025 Acts, Pamphlet No. 3).

Full Breakdown

Section 150.40(A) of the Building Regulations chapter requires that permit applications include plans and specifications showing, among other systems, the layouts of the electrical, plumbing, heating, ventilating, and air conditioning systems, before the county will process the request. Section 150.40(B) then makes the permit itself mandatory: a permit shall be obtained before beginning construction, alteration, repair, or placement of any building or structure, and every permit is issued by the Building Commissioner, with fees paid to the County Planning and Building Department. The Uniform Schedule at § 37.25(D) prices that electrical review at $60 for all principal and accessory uses, the same rate charged for a plumbing permit review.

The substantive building standard behind that permit is § 150.39, which incorporates by reference the building rules of the State Fire Prevention and Building Safety Commission under 675 I.A.C., along with the International Building Code for commercial work, as later amended; the county does not separately name the National Electrical Code in this chapter, so electrical work runs through those incorporated state and ICC rules rather than a locally cited NEC edition. Once a permit issues, § 150.41 requires the Building Commissioner to review every application for compliance, and § 150.42 requires inspection of the work as it proceeds, with reinspection ordered if work is not ready when the inspector arrives. Section 150.46 requires all work to be performed in a good and workmanlike manner according to accepted trade standards, and § 150.45 bars a certificate of occupancy until the work, including its electrical systems, complies with the subchapter.

Violations & Fines

Doing electrical work covered by this subchapter without a permit, or contrary to the approved plans, is unlawful under § 150.47 and punishable under § 150.99(C) by a fine of not less than $10 nor more than $200, with each day of the violation a separate offense. The Building Commissioner can also halt the work with a written stop work order under § 150.44, and withhold a certificate of occupancy under § 150.45 until the electrical work passes inspection.

Frequently Asked Questions

Do I need a permit for electrical work in Hendricks County?
Yes. Section 150.40(B) requires a permit before any construction, alteration, or repair of a structure, and subsection (A) specifically requires the application plans to show the electrical system layout before the Building Commissioner will issue it.
How much does an electrical permit review cost?
The Planning and Building Department charges a flat $60 review fee under § 37.25(D) for an electrical permit covering any principal or accessory use, the same rate it charges for a plumbing permit review on the same job.
What electrical code does the county enforce?
The county incorporates the building rules of the State Fire Prevention and Building Safety Commission under 675 I.A.C. and the International Building Code by reference in § 150.39; it does not separately cite a National Electrical Code edition in this chapter.
What if electrical work is done without a permit?
It is unlawful under § 150.47, fined $10 to $200 per day under § 150.99(C), and the Building Commissioner can issue a written stop work order under § 150.44 until the permit is obtained and the work is inspected and approved.
Can I get a certificate of occupancy before the electrical work is inspected?
No. Section 150.45 bars a certificate of occupancy for any building or structure until it was placed, erected, altered, or repaired in compliance with the subchapter, and occupying it beforehand without a certificate is itself unlawful under the same chapter.

Sources & Official References

Other rules in Hendricks County

All Hendricks County rules

Compare Hendricks County to another location·View the Indiana building safety overview

Get notified when Electrical Permits in Hendricks County, IN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.