Kennewick, WA Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Electrical authority
WA Dept. of Labor & Industries, not the City
Governing section
KMC 15.48.010 (Ord. 1395, 1968)
Building code cross-reference
KMC 15.08.130, Electrical Code of Washington
Permits/inspections
Delegated entirely to state L&I
City building code penalty
Misdemeanor, up to $1,000 / 90 days

Summary

Kennewick does not issue its own electrical permits. Under KMC 15.48.010, the city has ceded electrical permitting and inspection to the Washington State Department of Labor and Industries, whose electrical code and rules govern wiring, equipment, and systems inside city limits, per KMC 15.08.130's scope provision.

In lieu of an electrical code in the City, rules and regulations as set forth by the Department of Labor and Industries, State of Washington will prevail. All electrical permits and inspections are delegated to the above-mentioned authority. ... This chapter governs the electrical components, equipment and systems used in buildings and structures covered by this code. Electrical components, equipment and systems shall be designed and constructed in accordance with the provisions of the Electrical Code of the State of Washington.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 19 Update 2).

Full Breakdown

Kennewick's own municipal code does not adopt an electrical code. ' That means a Kennewick property owner or contractor pulls electrical permits directly from L&I, not from the City's Building Division, and L&I inspectors, not city staff, sign off on the wiring. 1 of the adopted building code to say that electrical components, equipment, and systems used in Kennewick buildings and structures 'shall be designed and constructed in accordance with the provisions of the Electrical Code of the State of Washington,' rather than a locally written chapter.

060(2) requires a separate plumbing, electrical, or mechanical permit for any item otherwise exempted from the general building permit, so an exempt shed or platform does not carry an automatic pass on electrical work performed inside it. 04) governs disputes over the city's own building permits, while electrical permit and inspection questions run through the state agency's own process.

Violations & Fines

Because state law delegates electrical permitting to L&I, electrical violations are enforced by the state's Department of Labor and Industries, not through Kennewick's own Title 15 penalty schedule. Other Title 15 violations, including working without a required building permit, are misdemeanors under KMC 15.04.070, punishable under KMC 1.12.010 by a fine up to $1,000, up to 90 days in jail, or both.

Frequently Asked Questions

Who issues electrical permits in Kennewick?
Not the City. KMC 15.48.010 states that, in lieu of a city electrical code, the rules of the Washington State Department of Labor and Industries prevail, and all electrical permits and inspections are delegated to L&I rather than Kennewick's Building Division.
What code governs electrical work on a Kennewick building?
KMC 15.08.130 requires that electrical components, equipment, and systems in city buildings be designed and constructed under the Electrical Code of the State of Washington, the same code L&I enforces statewide, not a Kennewick-specific chapter.
Can I appeal a denied electrical permit through the City?
No. Because permitting and inspection authority sits with Washington L&I under KMC 15.48.010, disputes over an electrical permit go through the state agency's own process rather than Kennewick's Chapter 4.04 building appeals route.
Does an exempt building project still need a separate electrical permit?
Yes. KMC 15.08.060(2) requires a separate electrical permit for otherwise permit-exempt work like sheds or platforms unless the work itself is also exempted, and that permit still comes from state L&I under KMC 15.48.010.

Sources & Official References

Other rules in Kennewick

All Kennewick rules

Compare Kennewick to another location·View the Washington building safety overview

Get notified when Electrical Permits in Kennewick, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.