Mosinee, WI Building Safety: Electrical Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Code adopted
Wis. Adm. Electrical Code ILHR ch. 16
Permit exemption
Broken sockets/switches/receptacles only
Licensing
City-licensed electrician required
Inspection point
After rough-in, before covering
Compliance certificate
Required before using the wiring

Summary

Mosinee adopts the Wisconsin Administrative Electrical Code by reference and requires a building inspector permit before any wiring or electrical equipment is installed or altered, under Sec. 42-1366. Only repairs to broken sockets, switches or base receptacles skip the permit, and all other electrical work in the city must be done by a city-licensed electrician.

(a)State code applies. All electrical work, including the placing of wires and other equipment, shall conform to the Wisconsin Adm. Electrical Code ILHR vol. 2, ch. 16 and amendments and revisions adopted to date, which is made by reference a part of this section, except that the remaining provisions of this section shall apply.(b)Permit. No electric wiring or other equipment shall be installed or altered without first securing a permit therefor from the building inspector, except that repairs or replacements of broken or defective sockets, switches or base receptacles may be made without a permit. ... (d)License required. All electrical work to be done in the city shall be done only by an electrician licensed by the city except that a property owner may make repairs or installations on his own property, provided that a permit is issued and the work is done in compliance with this article.

Full Breakdown

Sec. 42-1366(a) makes the Wisconsin Adm. Electrical Code, ILHR vol. 2, ch. 16, part of the city's code by reference, along with its amendments and revisions to date. Subsection (b) then requires a permit from the building inspector before installing or altering any electric wiring or other equipment, exempting only repairs or replacements of broken or defective sockets, switches or base receptacles. The permit application must state the planned work, alterations, and the equipment and materials to be used, and any later deviation from that plan has to be resubmitted for the building inspector's approval.

Subsection (c) requires the installer to call for inspection after the wiring is roughed in and before it is covered, or after outside wiring work is finished; the building inspector then inspects and, if the work meets the state electrical code, issues a certificate of compliance, without which it is unlawful to use the equipment. Subsection (d) limits who can do the work: electrical work in the city must be done by an electrician licensed by the city, though a property owner may do repairs or installations on his own property if a permit is issued and the work complies with the article. The license fee for city electricians is set by the common council from time to time and paid to the administrator.

Violations & Fines

Using electrical equipment before the building inspector issues a certificate of compliance is unlawful under Sec. 42-1366(c). Doing electrical work in the city without holding a city electrician's license, other than a property owner's own repairs under a proper permit, also violates subsection (d). Sec. 42-1355 lets the building inspector revoke the electrical permit by written notice at the job site for noncompliance, and further work under a revoked permit is unlawful.

Frequently Asked Questions

Do I need a permit to rewire part of my house in Mosinee?
Yes, unless you are only repairing or replacing a broken socket, switch or base receptacle. Sec. 42-1366(b) requires a permit from the building inspector for installing or altering electric wiring or equipment.
Can I do my own electrical work in Mosinee?
A property owner may make repairs or installations on his own property under Sec. 42-1366(d), but a permit must still be issued and the work must comply with the article; otherwise, only a city-licensed electrician may do the work.
What inspection is required for electrical work?
Sec. 42-1366(c) requires the installer to notify the building inspector after the wiring is roughed in and before it is covered, or after outside wiring is complete, so the inspector can issue a certificate of compliance.
Can I use new wiring before it is inspected?
No. Sec. 42-1366(c) makes it unlawful to use the electrical equipment until the building inspector has issued a certificate of compliance following inspection of the completed work.

Sources & Official References

Other rules in Mosinee

All Mosinee rules

Compare Mosinee to another location·View the Wisconsin building safety overview

Get notified when Electrical Permits in Mosinee, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Marathon County handle electrical permits.

Wausau, WI
Some Restrictions