Key Facts

Permit issuer
Department of Building Inspection
Adopted standard
National Electrical Code, NFPA 70
Concealment notice
24 hours before covering wiring
Residential 100-amp fee
$50 (§1361.04(a))
Re-inspection fee
$25

Summary

In the City of Oregon, Ohio, no one may perform electrical construction work or alterations in any building without first applying to the Department of Building Inspection and obtaining a permit under Codified Ordinances Section 1309.06. Wiring installed to National Electrical Code standards is deemed to meet the City's minimum safe-practice standard, and a Certified Electrical Inspector signs off on plans, rough-in and final work.

1309.06 ELECTRICAL WIRING AND EQUIPMENT. ... (a) General. (1) Except as otherwise provided in this Code, electric wiring and equipment installed in conformity with the recommendations and requirements of the National Electrical Code NFPA #7O, shall be accepted as being in conformity with accepted safe practice. ... (c) Permit Required. No individual. firm, or corporation shall attempt to do or cause to be done, any electrical construction work or alterations within any building within the City of Oregon without first making application to the Department of Building Inspection and obtaining a permit to do or have done such work. This permit must be upon a printed form provided for that purpose.

Full Breakdown

06, Electrical Wiring and Equipment, sits in Chapter 1309, General Requirements, and treats the National Electrical Code, NFPA 70, as the City's baseline for safe practice: subsection (a) says wiring installed to the Code's recommendations is accepted as conforming, but calls that only a minimum standard, warning that larger wire, more circuits and better equipment are often needed for good, convenient service. Subsection (b) requires plans and specifications with the permit application detailed enough for the Certified Electrical Inspector to verify the scope of work, equipment locations and circuit capacities, though the Inspector may waive plans when the application already describes the work adequately.

Subsection (c), Permit Required, is the operative rule: no individual, firm or corporation may do or cause to be done any electrical construction work or alteration in any building in the City of Oregon without first applying to the Department of Building Inspection and obtaining a permit on the City's printed form. Subsections (d) and (e) then set the inspection sequence: wiring may not be concealed without the Inspector's authorization, the installer must give at least 24 hours' notice before work is covered, roughing-in must be inspected and approved before concealment, and multi-meter service equipment must be permanently labeled by subdivision before final inspection.

04 prices permits by category, for example $50 for a residential 100-amp service and $10 for each additional 50 amps, with a $25 re-inspection fee and a $150 appeal filing fee available if a permit is denied.

Violations & Fines

Doing electrical work without the Department of Building Inspection permit required by Section 1309.06(c), concealing wiring before the Certified Electrical Inspector authorizes it, or failing to correct nonconforming work flagged on inspection are violations of the Building Code. Part Thirteen's general penalty, Section 1305.99, makes noncompliance with a Building and Zoning Inspection order a misdemeanor of the first degree where no other penalty applies.

Frequently Asked Questions

Do I need a permit to rewire a room in Oregon, Ohio?
Yes. Section 1309.06(c) requires anyone doing electrical construction work or alterations in any building in the City to apply to the Department of Building Inspection and obtain a permit before starting, using the City's printed application form.
What electrical code does the City of Oregon follow?
Section 1309.06(a) accepts wiring installed to the National Electrical Code, NFPA 70, as meeting the City's safe-practice standard, but the ordinance calls that only a minimum: it notes that larger wire, more circuits and better equipment are often needed for satisfactory service.
How much does an electrical permit cost?
Fees are set in Section 1361.04. A residential 100-amp service permit runs $50, with $10 for each additional 50 amps of service size, a $25 re-inspection fee, and a $150 fee to appeal a permit denial under the related property maintenance chapter.

Sources & Official References

Other rules in Oregon

All Oregon rules

Compare Oregon to another location·View the Ohio building safety overview

Get notified when Electrical Permits in Oregon, OH changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Lucas County handle electrical permits.

Toledo, OH
Some Restrictions