Key Facts

Adopted electrical code
National Electrical Code, as amended (§ 5.3.2(c))
Permit required before
Any electrical install, alteration, or repair
Working without a permit penalty
100% of usual permit fee, added on
Required electrical inspections
Temp pole, underground, rough-in, final
Contractor requirement
Current Georgia state electrical license
Permit expires if unstarted
6 months after issuance
Appeal of denial
30 days, $50 fee, to Construction Board

Summary

Roswell adopts the National Electrical Code, as amended, for every electrical installation in the city (Code of Ordinances § 5.3.2(c)) and requires a permit from the chief building inspector before any electrical work begins, backed by staged inspections, licensing checks, and a 100% fee penalty for starting without one.

(c)Electrical. The provisions of the National Electrical Code, as amended, shall apply to the installation of electrical systems, including alterations, repairs, replacement, equipment, appliances, fixtures, fittings and appurtenances thereto.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 17 | Unified Development Code: Supplement 5).

Full Breakdown

2(c) of the Roswell Code of Ordinances states: "Electrical. 1, and where any of those codes conflicts with a Roswell ordinance, the state code prevails to the extent of the conflict. 23). 5). 39(b): a temporary pole inspection after the power pole is grounded and ready to energize, an underground inspection after conduit or cable is laid and before backfill, a rough-in inspection after framing is up but before wall or ceiling coverings go on, and a final inspection after all fixtures are installed and connected, before the structure is occupied. 40 must be paid in full before a certificate of occupancy issues. 6).

Violations & Fines

Starting electrical work before a permit issues draws a penalty equal to 100 percent of the usual permit fee, on top of the required fee itself (§ 5.4.28). The chief building inspector may revoke a permit for misrepresentation in the application or for work found in violation of the adopted codes (§§ 5.4.33, 5.4.34). Because Chapter 5 sets no separate criminal penalty for electrical permit violations, offenses fall under the Code's general penalty, § 1.1.3: a fine up to $2,000.00, imprisonment up to 180 days, and/or community service up to 180 days, with each day of continued violation a separate offense.

Frequently Asked Questions

Does Roswell, Georgia require an electrical permit for wiring work?
Yes. Section 5.4.1 requires anyone who wants to install, alter, repair, remove, or replace an electrical system to first apply to the chief building inspector and obtain a permit before starting work, and § 5.3.2(c) applies the National Electrical Code, as amended, to that installation.
What code governs electrical installations in Roswell?
The National Electrical Code, as amended, under Code of Ordinances § 5.3.2(c). It is one of the Georgia State Minimum Standard Codes the city adopts by reference in § 5.3.1, and it controls over a conflicting city ordinance to the extent of the conflict.
What inspections does electrical work go through in Roswell?
Four inspections under § 5.4.39(b): a temporary pole inspection once the power pole is grounded and ready to energize, an underground inspection before backfill covers conduit or cable, a rough-in inspection before walls or ceilings are covered, and a final inspection before the building is occupied.
What happens if electrical work starts before a permit is issued in Roswell?
Section 5.4.28 imposes a penalty equal to 100 percent of the usual permit fee, charged in addition to the required permit fee itself. The chief building inspector can also revoke a permit later for misrepresentation or code violations under §§ 5.4.33-5.4.34.
Can I appeal if the city denies my electrical permit application?
Yes. Under §§ 5.5.4 and 5.5.6, the applicant may appeal the chief building inspector's decision to the Construction Board of Adjustment and Appeals by filing written notice within 30 calendar days and paying a $50.00 filing fee.

Sources & Official References

Other rules in Roswell

All Roswell rules

Compare Roswell to another location·View the Georgia building safety overview

Get notified when Electrical Permits in Roswell, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Electrical Permits in Nearby Cities

How other cities in Fulton County handle electrical permits.

Atlanta, GA
Some Restrictions
Sandy Springs, GA
Some Restrictions