Key Facts
- Adopted code
- 2022 CEC (based on 2017 NEC)
- Governing section
- SBMC § 15.04.020(B)(3)
- Permit lapses after
- 180 days without inspection
- Max misdemeanor penalty
- $1,000 fine / 6 months jail
- Enforcing office
- Building Official
- Chapter effective
- Ord. MC-1433, 12-21-2016
Summary
San Bernardino enforces electrical work under the 2022 California Electrical Code (based on the 2017 NEC), adopted into local law at San Bernardino Municipal Code § 15.04.020(B)(3). Any wiring, service upgrade or fixture installation must comply with that code and secure a permit and inspection from the Building Official before work starts.
(B) The city does formally adopt the state model building codes into local law as listed below: ...
(3) 2022 California Electrical Code, Title 24, Part 3 (based on 2017 NEC); ...
§ 15.04.030 APPLICABILITY.
(A) It shall be unlawful to erect, construct, change the occupancy, alter, repair, rehabilitate, remove, move or maintain any building or structure, or grade or alter any land, in the city in violation of, or without complying with, the appropriate provisions of this chapter.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-2: Supplement contains: Local legislation current through Ord. MC-1666, passed 8-5-2026).
Full Breakdown
The City of San Bernardino does not write its own wiring rules. 020(B)(3) of the Building Code chapter formally adopts the 2022 California Electrical Code, Title 24, Part 3 of the California Code of Regulations, itself based on the 2017 National Electrical Code, as the administrative and technical standard for every electrical installation, alteration or repair inside city limits. 030(A) makes it unlawful to erect, construct, alter, repair or maintain any building or structure, including its electrical systems, without complying with the adopted code, which is how a permit and inspection from the Building Official become required before energizing new circuits, upgrading a service panel or wiring an addition.
020(C). 050 gives the permittee 180 days to obtain an inspection and show substantial progress; failing to do so is treated as prima facie evidence the work was abandoned, and the permit expires automatically, requiring a new application. The chapter was added by Ord. MC-1433 on December 21, 2016, and the adoption list has since been updated by Ord. MC-1521 (2019), Ord. MC-1525 (2020) and Ord. MC-1643, passed October 2, 2024, to keep San Bernardino current with each new triennial state code cycle.
Violations & Fines
Working without a required electrical permit, or continuing work after a stop-work order issued under § 15.04.260, is a misdemeanor, and each day the violation continues is charged as a separate offense. Under the city's general penalty at § 1.12.010(A), a misdemeanor building-code violation carries up to six months in county jail, a fine of up to $1,000, or both, plus reimbursement of the city's investigation and enforcement costs.
Frequently Asked Questions
Does San Bernardino require a permit for electrical work?
What happens if I don't call for an inspection after pulling a permit?
What edition of the electrical code applies right now?
Can I keep working after the city issues a stop-work order?
Sources & Official References
Other rules in San Bernardino
California rules heatmap·Compare San Bernardino to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Electrical Permits in Nearby Cities
How other cities in San Bernardino County handle electrical permits.