Victorville, CA Building Safety: Electrical Permits (2026)
Key Facts
- Adopted electrical code
- 2025 California Electrical Code / 2023 NEC
- Governing section
- Municipal Code Sec. 16-5.09.020
- Permit fees
- Per City's adopted fee schedule
- Application expiration
- 180 days without permit issuance
- Permit expiration
- 12 months with no work or inspection
Summary
Victorville requires electrical work to follow the 2025 California Electrical Code, adopted by reference with the 2023 National Electrical Code and California amendments; permits and fees run through the Building Department under the City's adopted fee schedule rather than a flat rate written into the ordinance.
The 2025 Edition of the California Electrical Code known as the California Code of Regulations, Title 24, Part 3, incorporating by reference, the 2023 National Electrical Code, published by the National Fire Protection Association with California amendments, as hereinafter modified is designated and adopted by reference as the electrical code of the City. One true copy of said California Building Code is on file in the Building Department and is available for public inspection.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 57).
Full Breakdown
Section 16-5.09.020 of the Municipal Code adopts the 2025 Edition of the California Electrical Code, known as the California Code of Regulations, Title 24, Part 3, incorporating by reference the 2023 National Electrical Code published by the National Fire Protection Association with California amendments, as the City's electrical code, with a true copy kept on file in the Building Department for public inspection. That adoption is what makes an electrical permit mandatory for covered work, since Article 9 operates under the same Administrative Building Code permit framework set out in Article 1.
Section 16-5.09.030 sets electrical permit fees in accordance with the adopted fee schedule, meaning the City Council's current fee resolution rather than a dollar figure fixed in the ordinance text. Because Article 9 has no separate permit-procedure sections of its own, an electrical permit application expires after 180 days without issuance under Section 16-5.01.100, and an issued electrical permit expires after twelve months of no completed work or no requested inspection under Section 16-5.01.110; resuming after a lapse of less than a year costs half the original permit fee, while a lapse over a year requires a full new permit and fee.
Violations & Fines
Electrical work performed without a Building Department permit is subject to Code Enforcement citation, a stop-work order, and the standard after-the-fact permitting process, which can require exposing completed wiring for inspection before it can be approved or a certificate of occupancy issued.
Frequently Asked Questions
What electrical code does Victorville use for permits?
How much does an electrical permit cost in Victorville?
How long is an electrical permit valid once issued in Victorville?
Sources & Official References
Other rules in Victorville
California rules heatmap·Compare Victorville to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Electrical Permits in Nearby Cities
How other cities in San Bernardino County handle electrical permits.