Newport Beach, CA Building Safety: Green Building Code (2026)
Key Facts
- Adopted code
- 2025 California Green Building Standards Code (CALGreen)
- Governing chapter
- Municipal Code Chapter 15.11, Section 15.11.010
- C&D debris deadline
- 10 calendar days of demolition, Section 6.04.150
- Diversion violation
- Infraction, $100-$500 fines, Section 1.04.010(A)
- Code availability
- Kept in Building Official's office for public inspection
- Latest re-adoption
- Ordinance 2025-23, Section 9 (2025)
Summary
Newport Beach adopts the 2025 California Green Building Standards Code (CALGreen) as the Newport Beach Green Standards Code under Chapter 15.11 of the Municipal Code. The Building Official keeps a copy on file for public inspection under Health and Safety Code Section 18942(e)(1), and contractors demolishing a structure must divert construction and demolition debris from disposal and clear the site within ten calendar days.
The City Council adopts and incorporates by reference, as though set forth in full in this section, the 2025 Edition of the California Green Building Standards Code. The various parts of this code shall constitute and be known as the “Newport Beach Green Standards Code.” ... All owners, contractors and builders of structures shall, at their sole cost and expense, comply with all requirements of Section 15.11.010 to divert construction and demolition debris from disposal. All construction and demolition debris shall be removed from the lot and all nearby premises utilized in such construction within ten (10) calendar days of demolition and said lot and premises shall be left in a sightly condition.
Full Breakdown
Chapter 15.11 of the Newport Beach Municipal Code adopts the 2025 Edition of the California Green Building Standards Code by reference, styling the compiled provisions the "Newport Beach Green Standards Code." Section 15.11.010 requires the Building Official to keep a copy of the code on file and available for public inspection, citing California Health and Safety Code Section 18942(e)(1) as the statutory basis for local adoption. The city has re-adopted the chapter with each triennial code cycle, most recently by Ordinance 2025-23 Section 9 (2025), following Ordinance 2023-22 Section 706 (2023) and Ordinance 2022-26 Section 9 (2022), so the version on file always tracks the current statewide CALGreen edition rather than an older one.
The green code's diversion mandate is enforced through the solid waste chapter: Municipal Code Section 6.04.150, Removal of Construction and Demolition Debris, requires every owner, contractor and builder to comply with "all requirements of Section 15.11.010 to divert construction and demolition debris from disposal," at their own cost. Debris from any construction or demolition project must be hauled off the lot and any nearby premises used during the work within ten calendar days of demolition, and the site must be left in a sightly condition. That ten-day clock and the diversion duty apply on top of any CALGreen-mandated recycling requirements carried in the adopted state code itself.
Building permit applicants confirm CALGreen compliance as part of plan review by the Building Division before a permit issues; the Building Official administers Chapter 15.11 alongside the parallel Administrative Code adopted at Chapter 15.02, which governs permit fees, investigation fees for work started without a permit, and demolition notice requirements citywide.
Violations & Fines
Under Municipal Code Section 6.04.230, failing to comply with the debris-diversion duty in Section 6.04.150, and by extension Section 15.11.010, is an infraction under Section 1.04.010(A): fines run up to $100 for a first violation, $200 for a second within one year, and $500 for each further violation of the same ordinance in that year. Work started without required permits triggers a separate investigation fee under amended Section 109.4 (Section 15.02.110), equal to the permit fee, regardless of whether a permit later issues.
Frequently Asked Questions
Does Newport Beach have its own green building code?
How long do I have to clear construction debris after demolishing a building?
What happens if I don't divert or remove construction debris on time?
Sources & Official References
Other rules in Newport Beach
California rules heatmap·Compare Newport Beach to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Green Building Code in Nearby Cities
How other cities in Orange County handle green building code.