Skip to main content
CityRuleLookup

Apex, NC Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Footing inspection
Before footings installed
Concrete inspection
Before structural pour
Framing inspection
Before framing concealed
Final inspection
Required before occupancy
Enforced by
Town code enforcement officer

Summary

Apex builders must notify the code enforcement officer and receive approval before footings, before structural concrete pours, before framing is concealed, and again at final completion: occupancy is barred until that last inspection passes.

The builder or permit holder, or such person's agent, foreman, or superintendent shall notify the code enforcement officer and receive approval: (1) Before footings are installed; (2) Before placing any concrete that is to be structurally reinforced; (3) Before any framing is concealed; (4) Promptly following final completion; no occupancy shall be permitted prior to this inspection.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 3).

Full Breakdown

Apex Town Code § 5-27 requires the builder, permit holder, or their agent, foreman, or superintendent to notify the code enforcement officer and get approval at four points: before footings are installed, before any structurally reinforced concrete is poured, before framing is concealed, and promptly after final completion, no occupancy is permitted before that last inspection. Skipping any required notification is itself a violation under § 5-27(b). A certificate of occupancy under § 5-30 then follows final inspections, confirming the building conforms to the town's regulatory codes and zoning ordinance before anyone can move in.

Violations & Fines

Failing to notify the code enforcement officer and obtain approval before footings, concrete pours, or framing concealment is itself a violation of § 5-27, separate from any underlying code defect.

Frequently Asked Questions

When must an Apex builder call for a required inspection?
Before footings are installed, before structurally reinforced concrete is poured, before framing is concealed, and again promptly after final completion, per Apex Town Code § 5-27.
Can I occupy a new building before the final inspection?
No. Apex Town Code § 5-27(a)(4) bars occupancy until the final completion inspection has been made, and § 5-30 requires a certificate of occupancy.
What happens if a required inspection notice is skipped?
It is itself a separate violation of Apex Town Code § 5-27(b), regardless of whether the underlying work is sound.

Sources & Official References

Other rules in Apex

All Apex rules

Compare Apex to another location·View the North Carolina building safety overview

Get notified when Building Inspections in Apex, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Wake County handle building inspections.

Raleigh, NC
Some Restrictions
Cary, NC
Some Restrictions