Key Facts

Notice required
24 hours before each inspection
Enforcing agency
Building and Fire Officials, Dept. of Planning, Engineering & Permits
Special inspection fee
$50.00 per additional inspection
Final inspection
Required before Certificate of Occupancy
Penalty
Misdemeanor, separate offense each day
Governing section
Code of Ordinances Sec. 7-1-3, Section 105.6

Summary

Before any Birmingham building permit closes out, the Building and Fire Officials must sign off on a fixed sequence of inspections under Code of Ordinances Sec. 7-1-3, Section 105.6: footing and foundation, concrete slab, framing, lath and gypsum board, and a final inspection. Contractors must give 24 hours' notice before each stage, and no work may be covered until it is released.

105.6 Required Inspections. It shall be the responsibility of the permit holder/contractor to give reasonable advance notice to the Building and Fire Officials when work is ready for test or inspection. Except in case of emergency this notice should be given 24 hours prior to the requested inspection unless otherwise specified. The Building and/or Fire Official, upon notification from the permit holder or his agent, shall make the following inspections and such other inspections as necessary, and shall either release that portion of the construction or shall notify the permit holder or his agent of any violations which must be corrected in order to comply with this Code: 105.6.1 Footing and foundation inspection...105.6.4 Frame inspection. Framing inspections shall be made after the roof deck or sheathing, all framing, fire blocking and bracing are in place and pipes, chimneys and vents to be concealed are complete and the rough electrical, plumbing, heating wires, pipes and ducts are approved...105.6.9 Final inspection. The final inspection shall be made after all work required by the building permit is completed.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 3).

Full Breakdown

Birmingham's Administration chapter of the technical code, Code of Ordinances Sec. 7-1-3, sets out the inspection sequence a permit holder must follow once a construction, fire protection, electrical, elevator, escalator, gas, mechanical, or plumbing permit is issued. 6 requires the permit holder or contractor to give the Building and/or Fire Official 'reasonable advance notice' before work is ready for test or inspection, ordinarily 24 hours except in an emergency. The Official then either releases that portion of construction or lists the violations that must be fixed.

9). 8). 7 before a Certificate of Occupancy issues. 00 per inspection. 3 lets the Building, Code, or Fire Official issue a written stop work order, effective immediately, whenever work proceeds contrary to the Code or in a dangerous manner; in an emergency no written notice is required first. The Department of Planning, Engineering and Permits administers these inspections citywide.

Violations & Fines

Continuing work after a stop work order, or building past an inspection stage without the required sign-off, exposes the permit holder to prosecution under Section 114, Violations and Penalties: a misdemeanor, with each day the violation continues counted as a separate offense, punished within the limits of Section 1-1-6 of the General Code. The Building Official may also withhold further permits from anyone who has not completed inspections on previously started work.

Frequently Asked Questions

Who has to request each Birmingham building inspection?
Section 105.6 puts the burden on the permit holder or contractor, who must give the Building and/or Fire Official reasonable advance notice, ordinarily 24 hours, before work reaches a stage ready for test or inspection. The Official then inspects, and either releases that part of the construction to continue or notifies the holder in writing of violations that must be corrected before work proceeds further.
What happens if I build past an inspection stage without approval?
The Building or Fire Official can require the covered work to be exposed again for inspection, and continuing work in violation of the Code after notice is a misdemeanor under Section 114, with each day of continued violation treated as a separate offense punishable under Section 1-1-6 of the General Code.
Is there a fee if the city has to re-inspect my project?
Yes. Section 105.4 authorizes a 'Special Inspection Permit' with an additional $50.00 charge for each extra inspection required because the permit holder failed to comply with the Code on the first pass, on top of the standard permit and inspection fees already paid.
Does fire protection equipment get inspected separately from the building shell?
Yes. Section 105.7 requires the Fire Official to witness acceptance tests for underground fire service, sprinkler systems, standpipes, fire pumps, and fire alarm systems, each with its own hydrostatic, flush, or functional test, before a Certificate of Occupancy or Completion can be issued.

Sources & Official References

Other rules in Birmingham

All Birmingham rules

Compare Birmingham to another location·View the Alabama building safety overview

Get notified when Building Inspections in Birmingham, AL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Jefferson County handle building inspections.

Hoover, AL
Some Restrictions
Vestavia Hills, AL
Some Restrictions