Birmingham, AL Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit required for
Erect, alter, repair, move, demolish structures/systems
Key exemptions
13 listed, e.g. shingles, small accessory sheds
Application lapse
Deemed abandoned after 6 months unfiled
Work-start deadline
Must start within 90 days of issuance
Fee if work starts first
Doubled under Sec. 104.2
Repeat violation add-on
$50.00 per additional violation

Summary

Birmingham law bars anyone from erecting, enlarging, altering, repairing, moving, converting, or demolishing a building, or installing electrical, gas, fire protection, mechanical, or plumbing systems, without first getting a permit from the Building and/or Fire Official under Code of Ordinances Sec. 7-1-3, Section 103. A short list of minor jobs, like painting or shingle repair on single-family homes, is exempt.

103 CONSTRUCTION PERMITS. A person, firm or corporation shall not erect, construct, enlarge, install, alter, repair, move, improve, remove, convert or demolish any building, structure, elevator, escalator, electrical, gas, fire protection, mechanical or plumbing system in the City of Birmingham, or cause the same to be done, without first obtaining a permit for such from the Building and/or Fire Official. 103.1 Application for permit. 103.1.1 When Required. Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any fire protection, electrical, elevator, escalator, gas, mechanical or plumbing system, the installation of which is regulated by this Code, or to cause any such work to be done, shall first make application to the Building and/or Fire Official and obtain the required permit for the work.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 3).

Full Breakdown

Section 103 of Birmingham's Administration chapter opens with a blanket prohibition: no person, firm, or corporation may erect, construct, enlarge, install, alter, repair, move, improve, remove, convert, or demolish any building, structure, elevator, escalator, or electrical, gas, fire protection, mechanical, or plumbing system in the city without first obtaining a permit from the Building and/or Fire Official. 1 requires any owner, authorized agent, or contractor who wants to do that work to first apply to the Building and/or Fire Official and obtain the permit. The section lists thirteen narrow exceptions where no permit is needed, among them portable heating or cooling equipment, self-contained refrigeration systems holding 10 pounds or less of refrigerant, accessory structures under 150 square feet on one- and two-family lots when the Planning Division signs off, roof shingle replacement on single-family homes, retaining walls under 3 feet from the top of the footing, and interior finish work like painting or carpeting.

A pool still needs no building permit itself, but its electrical and plumbing work and inspections do. 5, an application is deemed abandoned if no permit issues within 6 months of filing, though the Building Official can grant 90-day extensions for good cause. 1 gives the permit holder 90 days to start work or the permit becomes invalid, and work cannot sit idle for 90 days without lapsing either. 2 double automatically if work starts before the permit is obtained.

Violations & Fines

Working without the required permit doubles the normal fee under Section 104.2, and repeat violations within any 12-month period add a flat $50.00 on top of the doubled fee for each additional violation. The Building Official can also withhold further permits from anyone until all work previously started without a permit is properly permitted, and violating Section 103 is separately a misdemeanor under Section 114, punished as a separate offense for each day it continues.

Frequently Asked Questions

What work in Birmingham does not need a building permit?
Section 103.1.1 lists thirteen exceptions, including portable heating and cooling units, self-contained refrigeration systems with 10 pounds of refrigerant or less, roof shingle replacement on single-family homes, retaining walls under 3 feet measured from the footing top, accessory structures under 150 square feet approved by the Planning Division, and interior painting, carpeting, or cabinet work.
What happens if I start work before my Birmingham permit is issued?
Section 104.2 automatically doubles the permit fee for any work commenced before the necessary permit is obtained, and the Building Official may refuse further permits to that person until all previously unpermitted work is brought into compliance. A repeat violation within 12 months adds a flat $50.00 penalty on top of the doubled fee.
How long is a Birmingham building permit good for once issued?
Under Section 103.6.1 the permit becomes invalid if work is not started within 90 days of issuance, or if work is suspended or abandoned for 90 days after starting. The Building Official can grant one or more extensions of up to 90 days each for good cause shown in writing.

Sources & Official References

Other rules in Birmingham

All Birmingham rules

Compare Birmingham to another location·View the Alabama building safety overview

Get notified when Building Permits in Birmingham, AL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.