Greensboro, NC Building Safety: Building Inspections (2026)
Key Facts
- Notice before work starts
- Immediate; 24 hours before demolition
- Location/footing inspection
- After trenches dug, rebar placed, pre-concrete
- Rough-in inspection
- Before wall, ceiling or insulation cover
- Final inspection
- After each trade's work is complete
- Prerequisite for final building inspection
- Plumbing, electrical, mechanical, fire all approved
- Inspector entry power
- Any reasonable hour, per Section 6-62
Summary
Greensboro's building code lays out seven required inspection checkpoints, from location and footing through the final inspection, under City Code Section 6-61. The building inspector must be notified immediately when covered work begins, and 24 hours before any demolition, and the final plumbing, electrical, mechanical and fire inspections must all pass before a final building inspection is made.
(a)Notice to building inspector of beginning of work. The building inspector shall be notified immediately upon the beginning of the construction, alteration, repair or removal of any building for which a permit is required. He/she/they shall be notified not less than twenty-four (24) hours before the beginning of the demolition of any building.(b)When to call for inspection.(1)Location and footing inspection: After all trenches are excavated, all grade stakes are installed, all reinforcing steel and supports are in place and braced before pouring or placement of any concrete... (4)Rough-in inspection: When all building framing, electrical, plumbing, mechanical, or fire protection systems that will be hidden from view in the finished building have been installed and before wall, ceiling finish, or building insulation is installed... (7)Final inspection: After completion of the work authorized under the technical code for each trade. The final plumbing, electrical, mechanical, and fire inspections must be approved before the final building inspection will be made.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 132).
Full Breakdown
Section 6-61(a) requires immediate notice to the building inspector at the start of construction, alteration, repair or removal work under a permit, and at least 24 hours' notice before demolition begins. Section 6-61(b) then lists the seven inspection stages a builder must call for in order. The location and footing inspection happens after trenches are dug, grade stakes set and reinforcing steel placed, but before any concrete is poured; if the property line is in question, the builder must supply a licensed surveyor's survey. The under-slab inspection follows, covering anything that will be hidden under a concrete slab.
Next comes the foundation and crawl space inspection, checking supports, leveling, clearances and drainage. The rough-in inspection covers framing, electrical, plumbing, mechanical or fire protection systems before walls, ceilings or insulation cover them. The building framing inspection follows, with pipes, chimneys, vents, flashing and structural lintels left visible for the inspector. The insulation inspection comes after framing and rough-in pass and after the roof covering goes on, but before wall or ceiling covering. The final inspection closes out each trade's work. Section 6-61 states directly that the final plumbing, electrical, mechanical and fire inspections must be approved before the final building inspection can be made.
Section 6-62 gives the building inspector power to enter public or private property at any reasonable hour to enforce the code, and Section 6-63 requires the inspector to issue a certificate of compliance once completed work conforms to state law and city ordinances.
Violations & Fines
Pouring concrete, closing in framing, or covering rough-in work before the corresponding inspection is called for and passed leaves that stage unapproved and can require the work to be exposed again for inspection. Failing to notify the building inspector immediately at the start of work, or at least 24 hours before demolition, is itself a Section 6-61(a) violation. No final building inspection, and no certificate of compliance under Section 6-63, can be issued until the plumbing, electrical, mechanical and fire inspections have each separately passed.
Frequently Asked Questions
How many inspections does a Greensboro building permit require?
Can I pour concrete before a Greensboro footing inspection?
What must happen before my final building inspection in Greensboro?
Sources & Official References
Other rules in Greensboro
Compare Greensboro to another location·View the North Carolina building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Inspections in Nearby Cities