Greensboro, NC Building Safety: Building Permits (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit issued by
building inspector
Late-permit penalty
fee equals permit cost
Posted placard
required, visible from street
Demolition permit holders
licensed contractor or owner only
Base inspection fee
$85 for first $11,000

Summary

No one may start construction, alteration, repair, removal or demolition of a building in Greensboro without a written permit from the building inspector under City Code § 6-56, unless the work is exempt under the North Carolina State Building Code. Skipping the permit adds a late fee equal to the permit cost itself.

(a)No person shall commence or proceed with the construction, alteration, repair, removal or demolition of any single building or other structure or part thereof without a written permit therefor from the building inspector except for building construction that is exempted from permit requirements under the North Carolina State Building Code. The copy of the permit shall be kept on the premises for public inspection during the prosecution of the work and until completion of the same. An identification placard showing the permit number signed by the building inspector shall be conspicuously posted on the site readily visible from the street. ...(e)For failure of a person to apply for and obtain any building permit required prior to commencement of a construction job, there shall be an additional fee in an amount equal to the permit fee itself.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 132).

Full Breakdown

Section 6-56(a) bars commencing or proceeding with the construction, alteration, repair, removal or demolition of any building or structure, or part of one, without a written permit from the building inspector, except for work exempted under the North Carolina State Building Code. The permit must stay on the premises for public inspection throughout the job, and an identification placard bearing the permit number, signed by the building inspector, must be posted where it's visible from the street. Subsection (b) restricts demolition permits to a licensed general contractor, a demolition contractor, or the owner, and requires a state NESHAP number and asbestos removal permit for commercial demolition, or an accredited asbestos inspector's report for residential demolition.

Subsection (c) applies the same permit requirement to erecting, altering or repairing a billboard or sign, absent a Building Code exemption. Under subsection (d), the building inspector must approve or disapprove an application within a reasonable time if the proposed work conforms to this article, the zoning ordinance, and other applicable ordinances. Subsection (e) imposes a direct financial consequence for skipping the process: anyone who fails to apply for and obtain a required permit before starting a construction job owes an additional fee equal to the permit fee itself, on top of the regular fee schedule in § 6-64.

Violations & Fines

Working without the required permit triggers an additional fee equal to the standard permit fee under § 6-56(e), on top of the base fee set in § 6-64's cost schedule. The building inspector can also issue a stop-work order under § 6-44 for work proceeding without a permit or in violation of approved plans, halting the job until the owner brings it into compliance.

Frequently Asked Questions

Do I need a permit for a small repair job in Greensboro?
Only if the work isn't exempted under the North Carolina State Building Code. § 6-56(a) requires a written permit from the building inspector for construction, alteration, repair, removal, or demolition of any building, with narrow state-code exemptions covering minor work: check with the inspector's office before starting.
What happens if I build without a permit in Greensboro?
You owe an additional fee equal to the full permit fee under § 6-56(e), and the building inspector can issue a stop-work order under § 6-44 requiring the job to stop until you apply, pay, and bring the work into compliance with the approved plans.
Who can pull a demolition permit?
Only a general contractor licensed by the North Carolina Licensing Board for General Contractors, a demolition contractor, or the property owner, per § 6-56(b). Commercial demolitions also need a state NESHAP number and asbestos removal permit; residential demolitions need an asbestos inspection report from a state-accredited inspector.

Sources & Official References

Other rules in Greensboro

All Greensboro rules

Compare Greensboro to another location·View the North Carolina building safety overview

Get notified when Building Permits in Greensboro, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.