Key Facts

Citation
High Point Code § 9-2-41(a)
Issuing office
Director of Planning & Development
Covers
Construction, alteration, repair, demolition
Also required
Certificate of occupancy, § 9-2-49
Permit expires
6 months if work unstarted

Summary

Before building, rebuilding, altering, repairing, removing, or tearing down any structure in High Point, you need a written permit from the director of planning and development.

Building permit. No person shall commence or proceed with the construction, reconstruction, alteration, repair, removal or demolition of any building or other structure, or any part thereof, without a written permit therefor from the director of planning and development.(b)Plumbing permit. No person shall commence or proceed with the installation, a extension or general repair of any plumbing system without a written permit from the plumbing inspector.(c)Heating-air conditioning permit. No person shall commence or proceed with the installation, extension, alteration or general repair of any heating or cooling equipment system without a written permit from the heating-air conditioning inspector.(d)Electrical permit. No person shall commence or proceed with the installation, extension, alteration or general repair of any electrical wiring, devices, appliances or equipment without a written permit from the electrical inspector. (Ord. No. 7206/16-26, § 4, 5-16-16)

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 9 | Development Ordinance: Supplement 14).

Full Breakdown

Section 9-2-41(a) bars starting construction, reconstruction, alteration, repair, removal, or demolition of any building or structure in High Point without a written permit from the director of planning and development. Applications must include a scaled plat showing lot dimensions and building placement under § 9-2-48, and a separate certificate of occupancy, required before the structure can be used at all, must be applied for at the same time under § 9-2-49. Permit fees are set by city council, and under § 9-2-45 an issued permit lapses automatically six months after issuance if work never starts.

Violations & Fines

Building or altering a structure without the required permit violates § 9-2-41(a) and can trigger enforcement action; the director may also revoke an issued permit for material departures from approved plans or false statements, under § 9-2-44.

Frequently Asked Questions

What triggers the need for a building permit in High Point?
Any construction, reconstruction, alteration, repair, removal, or demolition of a building or structure requires a written permit from the director of planning and development under § 9-2-41(a).
Can I occupy a new High Point building right after getting the building permit?
No. Section 9-2-49 requires a separate certificate of occupancy before any new or altered building can be used or occupied.

Sources & Official References

Other rules in High Point

All High Point rules

Compare High Point to another location·View the North Carolina building safety overview

Get notified when Building Permits in High Point, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Permits in Nearby Cities

How other cities in this county handle building permits.

Greensboro, NC
Some Restrictions