Hamburg Village, NY Building Safety: Building Inspections (2026)
Key Facts
- Who calls for inspection
- The permit holder notifies the Code Enforcement Officer
- First inspection
- Work site, before the building permit is issued
- Last inspection
- Final inspection after all permitted work is completed
- Remote inspections
- Allowed at the officer's discretion if same level and quality
- Failed work
- Stays exposed until reinspected and found satisfactory
- Fee
- Due before or at each inspection (§ 123-18)
Summary
In the Village of Hamburg, work under a building permit must stay accessible and exposed until the Code Enforcement Officer or an authorized inspector accepts it. The permit holder calls for inspection at each listed stage, from footing and foundation through framing to a final inspection, and failed work stays exposed until it is corrected and reinspected.
A. Work to remain accessible and exposed. Work shall remain accessible and exposed until inspected and accepted by the Code Enforcement Officer or by an inspector authorized by the Code Enforcement Officer. The permit holder shall notify the Code Enforcement Officer when any element of work described in Subsection B of this section is ready for inspection. B. Elements of work to be inspected. The following elements of the construction process shall be inspected, where applicable: (1) Work site prior to the issuance of a building permit; (2) Footing and foundation; (3) Preparation for concrete slab; (4) Framing; (5) Structural, electrical, plumbing, mechanical, fire-protection, and other similar service systems of the building; (6) Fire resistant construction; (7) Fire-resistant penetrations; (8) Solid-fuel-burning heating appliances, chimneys, flues, or gas vents; ... (11) A final inspection after all work authorized by the building permit has been completed.
Full Breakdown
Village of Hamburg Code § 123-5A says work must remain accessible and exposed until the Code Enforcement Officer, or an inspector the officer authorizes, inspects and accepts it. The permit holder is the one who notifies the Code Enforcement Officer when an element of work is ready for inspection. Section 123-5B lists what gets inspected, where applicable: the work site before the building permit is issued, footing and foundation, preparation for concrete slab, framing, structural, electrical, plumbing, mechanical, fire-protection, and similar service systems, fire resistant construction, fire-resistant penetrations, solid-fuel-burning heating appliances, chimneys, flues, or gas vents, Energy Code items such as insulation, fenestration, and air leakage, installation of factory manufactured buildings and manufactured homes, and a final inspection after all permitted work is complete.
Under § 123-5C the Code Enforcement Officer or authorized inspector can accept a remote inspection in place of an in-person visit when it can be performed to the same level and quality. If a remote inspection does not supply enough information, an in-person inspection is performed. After each inspection, § 123-5D requires the work to be noted as satisfactory, or the permit holder to be told how the work fails, with a citation to the specific code provision not met. Noncompliant work stays exposed until it is brought into compliance, reinspected, and found satisfactory. The fee set under § 123-18 is due before or at the time of each inspection (§ 123-5E).
The inspections lead into the certificate of occupancy. Section 123-7A requires a certificate of occupancy or certificate of compliance for any work that is the subject of a building permit, and § 123-7B has the Code Enforcement Officer or an authorized inspector inspect the building, structure, or work before one issues. A temporary certificate of occupancy under § 123-7D is effective for a period not to exceed six months. Under § 123-3A the Code Enforcement Officer comes from the Town of Hamburg Building Inspection Department under the shared services agreement, unless the Village designates its own official.
Violations & Fines
Covering work before inspection or leaving failed work unfixed breaches § 123-5. A person who violates Chapter 123 faces a fine of not more than $250 per day of violation, or imprisonment not exceeding 10 days, or both, plus a civil penalty of not more than $250 for each day or part thereof (§ 123-17C). The Code Enforcement Officer can issue a stop-work order for work contrary to the Uniform Code or Energy Code (§ 123-6A(1)) and an order to remedy that sets a 30-day deadline (§ 123-17A).
Frequently Asked Questions
Who requests a construction inspection in the Village of Hamburg?
Can I cover framing before the inspector sees it?
Does the Village allow remote inspections?
Is there a fee for each inspection?
Sources & Official References
Other rules in Hamburg Village
New York rules heatmap·Compare Hamburg Village to another location·View the New York building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Inspections in Nearby Cities
How other cities in Erie County handle building inspections.