Jackson, MS Building Safety: Building Inspections (2026)
Key Facts
- Minimum inspections
- 3 (reference mark, footprint, final)
- Permit fee
- $40.00 nonrefundable per structure
- Permit lapses after
- 6 months without substantial work
- Administrator
- Dept. of Planning & Development
- Max penalty
- $500 fine or 90 days jail
Summary
Jackson requires at least three inspections before a floodplain development permit closes out: one at the base flood elevation reference mark, one at the structure's footprint before the slab pours, and a final inspection after the elevation certificate is submitted. The floodplain administrator in the planning and development department runs the process under Chapter 62 of the city code.
Perform a minimum of three inspections to ensure that all applicable ordinance and floodplain development requirements have been satisfied. The first inspection upon the establishment of the base flood elevation reference mark at the development site; the second upon the establishment of the structure's footprint prior to pouring the slab or the establishment of the lowest floor in an elevated foundation system; and the final inspection upon completion and submission of the required finished construction elevation certificate.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 55).
Full Breakdown
Jackson's floodplain permitting authority sits with the director of the department of planning and development, designated the floodplain administrator under Sec. 62-31. 00 per structure under Sec. 62-34, and the application must show existing or proposed structures, fill and drainage, plus, for a residential building, the proposed lowest floor elevation on FEMA Form 81-31, certified by a Mississippi-registered engineer or surveyor under Sec. 62-32(1). Once a permit issues, Sec. 62-33(3) obligates the administrator to perform at least three site inspections tied to the physical stages of construction: the base flood elevation reference mark before work begins, the structure's footprint before the slab is poured (or the lowest floor of an elevated foundation), and a final inspection after the permit holder submits the completed FEMA elevation certificate.
Sec. 62-32(2) adds that work performed before the as-built lowest-floor survey is submitted proceeds at the permit holder's own risk, and uncorrected deficiencies are cause for a stop-work order. A floodplain permit expires if substantial work has not begun within six months of issuance, or if work is discontinued for six months or more, under Sec. 62-35.
Violations & Fines
Violating any provision of Chapter 62, including failure to pass a required inspection, is a misdemeanor under Sec. 62-21: conviction carries a fine of not more than $500.00 or up to 90 days in jail, or both, plus costs. Each day the violation continues is a separate offense, and the floodplain administrator can also take other lawful action, including a stop-work order, to halt uninspected work.
Frequently Asked Questions
What triggers the first floodplain inspection in Jackson?
How much does a Jackson floodplain permit cost?
What happens if I build before submitting the lowest-floor survey?
Sources & Official References
Other rules in Jackson
Compare Jackson to another location·View the Mississippi building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.