Lacey, WA Building Safety: Building Inspections (2026)
Key Facts
- Underground stage
- After excavation and bedding, before backfill
- Rough-in stage
- Before wall or ceiling membranes are installed
- Final stage
- After all work required by the permit is completed
- Who requests
- The person doing the permitted work
- Test costs
- Apparatus, material and labor furnished by permit holder
- Permit lapse
- No inspection called within one hundred eighty days
Summary
In the City of Lacey, Washington, electrical work under a permit is inspected at set stages: underground, rough-in and final, plus any other inspection the code official requires. Work stays accessible and exposed until approved, and the person doing the work must notify the code official when it is ready for each inspection.
B. Required Inspections. 1. General. ... The code official, upon notification, shall make the inspections set forth in this section. ... b. Concealed work. Work shall remain accessible and exposed for inspection purposes until approved. ... c. Underground. Underground inspection shall be made after trenches or ditches are excavated and bedded, piping and conductors installed, and before backfill is put in place. ... d. Rough-in. ... Rough-in inspection shall be made after the roof, framing, fireblocking and bracing are in place and all wiring and other components to be concealed are complete, and prior to the installation of wall or ceiling membranes. ... f. Final inspection. The final inspection shall be made after all work required by the permit is completed. ... h. Approval required. Work shall not be performed beyond the point indicated in each successive inspection and test without first obtaining the approval of the code official. ... 6. Inspection requests. It shall be the duty of the person doing the work authorized by a permit to notify the code official that such work is ready for inspection.
Full Breakdown
LMC 14.13.070 has the code official make the required electrical inspections on notification. Concealed work must stay accessible and exposed until approved, and the code makes that the permit applicant's duty. Covered work that was never inspected can be ordered exposed, and neither the code official nor the City of Lacey is liable for the expense of removing or replacing material to allow inspection.
The stages run in order. The underground inspection comes after trenches or ditches are excavated and bedded and piping and conductors are installed, and before backfill. Where the soil holds rocks, broken concrete, frozen chunks or other rubble, or corrosive action will occur, the raceway, cable or conductors need protection such as granular or selected material, approved running boards or sleeves. The rough-in inspection comes after the roof, framing, fireblocking and bracing are in place and all concealed wiring is complete, and before wall or ceiling membranes go up. The final inspection comes after all work required by the permit is completed. The code official can also make or require other inspections.
Before work starts, the permit holder or an agent posts an inspection record card so the code official can enter results, and the card stays until final approval. No work proceeds past the point of an inspection without approval, and a portion that fails must be corrected and stay uncovered until the code official authorizes otherwise. Tests are performed by the permit holder and observed by the code official, with apparatus, material and labor furnished by the permit holder.
Inspectors carry city-issued identification, present credentials to occupants and request entry; for unoccupied premises they first make a reasonable effort to locate the owner.
For the building itself, LMC 14.04.015 amends Section 111.2 so the permittee requests a final inspection and certificate of occupancy on a city form signed by both the building owner and the building contractor. Under LMC 14.18.020 a permit also lapses if no inspection has been called for within one hundred eighty days, and a validly called inspection requires the work to be complete and ready.
Violations & Fines
Failing to comply with the electrical code, an order under it, or a permit condition is a misdemeanor under LMC 14.13.100. A written stop work order halts electrical work done contrary to the code or in a dangerous manner, and continuing after service brings penalties prescribed by law. Signs, tags or seals the code official posts cannot be removed or tampered with. LMC 14.17.080 caps a Title 14 misdemeanor at a fine of up to $5,000 and/or imprisonment of up to one year.
Frequently Asked Questions
When is the rough-in electrical inspection done in Lacey?
Who has to ask for the electrical inspection?
What if I cover the wiring before it is inspected?
Does passing an electrical inspection mean the work is legal?
What does the building final inspection involve in Lacey?
Sources & Official References
Other rules in Lacey