Gwinnett County, GA Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Footing/foundation inspection
Before concrete is placed
Framing inspection
Before walls are closed
Final inspection
After all permitted work done
Scheduling duty
Falls on the permit holder
Scope
Unincorporated Gwinnett County only

Summary

Gwinnett County's building official runs a fixed sequence of inspections, footing, framing, and final among them, and the permit holder must schedule each one under Code Appendix B § 110.3.

These county ordinances apply to unincorporated areas of Gwinnett County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

110.3. - Required inspections. The building official, upon notification from the permit holder or permit holder's agent, shall make the inspections set forth in Sections 110.3.1 through 110.3.10 and other such inspections as necessary, and shall either release that portion of the construction or notify the permit holder or the permit holder's agent of violations that are required to be corrected. The permit holder is responsible for scheduling the required inspections.

110.3.1. - Footing and foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel is in place. For concrete foundations, any required forms shall be in place prior to inspection. Materials for the foundation shall be on the job, except where concrete is ready mixed in accordance with ASTM C 94, the concrete need not be on the job.

110.3.2. - Concrete slab and under-floor inspection. Concrete slab and under-floor inspections shall be made after in-slab or under-floor reinforcing steel and building service equipment, conduit, piping accessories and other ancillary equipment items are in place, but before any concrete is placed or floor sheathing installed, including the subfloor.

110.3.3. - Rough Inspection.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 9).

Full Breakdown

§ 110.3 directs the building official to make the inspections listed in §§ 110.3.1-110.3.10 whenever notified by the permit holder, then either release that stage of construction or flag violations to correct. The listed stages include footing/foundation, concrete slab/under-floor, rough, framing, lath/gypsum board, fire-resistant penetration, energy efficiency, special, and final inspections. The permit holder is responsible for scheduling every required inspection. This applies to work permitted in the unincorporated county only.

Violations & Fines

§ 110.7 bars work from proceeding past an inspected point without building official approval; concealing uninspected work forces reopening. Non-compliance can draw a stop-work order (§ 111.3) and a $100-$1,000 fine or up to 60 days jail (§ 1-11).

Frequently Asked Questions

Who schedules Gwinnett County building inspections?
The permit holder or their agent must notify the building official when work is ready; § 110.3 lists the required stages from footing through final inspection.
Can I keep building past an uninspected stage?
No, § 110.7 blocks work beyond each inspection point until the building official approves it, and concealed work may have to be reopened.

Sources & Official References

Other rules in Gwinnett County

All Gwinnett County rules

Compare Gwinnett County to another location·View the Georgia building safety overview

Get notified when Building Inspections in Gwinnett County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.