Key Facts
- Re-inspection authority
- Subsection 110.3.8.1 added by § 15.08.065
- Re-inspection fee amount
- Set in the current City of National City Fee Schedule
- After a fee is assessed
- No further inspections until the fee is paid
- Grading pre-construction notice
- Not less than forty-eight hours before grading begins
- Annual fire inspection
- Groups A, C, F, H, I, L, M, S and open-flame Group B restaurants
- Other businesses
- In-person fire inspection every two years
Summary
In National City, the Building Official can charge a re-inspection fee under Municipal Code § 15.08.065 when work is not ready, corrections are not made, plans are not on site, access is refused, or the job departs from approved plans. Once a fee is assessed, no further inspections are performed until it is paid at the rate in the City Fee Schedule.
Re-inspections. A re-inspection fee may be assessed for each inspection or re-inspection when any of the following occurs: ... 1.The portion of work for which the inspection was called is not complete or the corrections previously required and called for are not made;2.Calling for an inspection before the job is ready for such inspection or re-inspection;3.The inspection record card or the approved plans are not posted or otherwise available to the inspector;4.Failure to provide access on the date for which the inspection is requested; or5.Deviating from the approved plans when such deviation or change required approval of the Building Official. ... To obtain a re-inspection, the permittee shall pay the re-inspection fee in accordance with the current City of National City Fee Schedule. In instances where a re-inspection fee has been assessed, no further inspections shall be performed until the fees have been paid.
Full Breakdown
National City writes its building inspection rules into Chapter 15.08, which amends the 2025 California Building Code. Section 15.08.065 adds Subsection 110.3.8.1, titled Re-inspections, to Section 110 of that code. The fee applies to each inspection or re-inspection in five situations: the work called for inspection is not complete or earlier corrections were not made; an inspection is requested before the job is ready; the inspection record card or approved plans are not posted or available to the inspector; nobody provides access on the requested date; or the work deviates from approved plans in a way that required Building Official approval. The amount comes from the current City of National City Fee Schedule, and the permittee must pay it before any further inspection is performed.
The staged sequence is clearest in the grading chapter. Section 15.70.080 adds Subsection J105.3, under which the permittee notifies the City Engineer for a pre-construction conference not less than forty-eight hours before grading begins, then for a toe of fill inspection before any fill is placed, an excavation inspection before the vertical depth exceeds 10 feet, a fill inspection before the lifts exceed 10 feet, a drainage device inspection before concrete is placed, a rough grading inspection at least twenty-four hours before it is made, and a final inspection. Retaining wall inspections follow the San Diego County Regional Standard Drawings or special engineering.
Existing buildings run on a separate cycle under Chapter 15.29. The Community Risk Reduction Division inspects every hotel, motel, lodging house, multi-family apartment house, school, hospital, jail and high-rise each year, along with Group A, C, F, H, I, L, M and S occupancies and Group B restaurants that use an open flame. Every other business gets an in-person inspection every two years under Section 15.29.040. Section 15.29.050 adds a yearly self-inspection program for low-risk businesses, with forms mailed annually and no filing with the City.
Violations & Fines
Under Section 15.08.065 the cost of an unready job, missing plans or blocked access is money and delay: the re-inspection fee is charged at the rate in the City Fee Schedule, and the Building Official performs no further inspections until it is paid. A business that skips its annual fire inspection under Section 15.29.030 faces administrative citations under Chapter 1.44 of the National City Municipal Code.
Frequently Asked Questions
What triggers a re-inspection fee in National City?
How much is the re-inspection fee and what happens if it goes unpaid?
How much notice does the City need for grading inspections?
Which National City businesses get an annual fire inspection?
Sources & Official References
Other rules in National City
California rules heatmap·Compare National City to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Inspections in Nearby Cities
How other cities in San Diego County handle building inspections.