Novato, CA Building Safety: Building Inspections (2026)
Key Facts
- Inspecting authority
- Building official or designee
- Rough inspection timing
- Before covering and before the framing inspection
- Flood hazard areas
- Sealed flood elevation certificate after lowest floor is placed
- CALGreen inspections
- Special inspector hired and paid by the permit holder
- Final approval
- Certificate of occupancy required before use or occupancy
- Who requests
- The permit holder or their agent
Summary
In the City of Novato, permitted work is inspected by the building official or a designee at set stages: footing and foundation, slab and under-floor, rough plumbing, mechanical, gas and electrical, framing, masonry, lath and gypsum board, energy, and final. No building or portion is used or occupied until all work is approved and a certificate of occupancy issues.
110.3 Required inspections. The building official or his/her designee, upon reasonable notification, shall make the inspections set forth herein. Reinforcing steel or structural framework of any part of any building or structure shall not be covered or concealed without first obtaining the approval of the enforcing agency. 110.3.1 Footing and foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel is in place. ... 110.3.3 Plumbing, mechanical, gas and electrical systems inspection. Rough inspection of plumbing, mechanical, gas and electrical systems shall be made prior to covering or concealment, before fixtures or appliances are set or installed, and prior to framing inspection. ... 110.3. ... 11 Final inspection. Final inspection shall be made after the permitted work is complete. The building, or portion thereof where the work occurred, shall not be used or occupied until all work has been approved by the building department and a certificate of occupancy has been issued by the building official.
Full Breakdown
Inspection rules sit in Section 110 of the administrative provisions adopted by Novato Municipal Code § 4-1.3. Work covered by a permit stays open to inspection by the building official or a designee, and the permit applicant must keep it visible and accessible until approved. Neither the building official nor the City is liable for the expense of removing or replacing material to allow inspection. Reinforcing steel and structural framework cannot be covered or concealed without approval.
The staged inspections follow construction order. Footing and foundation inspection comes after excavations are complete and required reinforcing steel is in place. Slab and under-floor inspection comes before concrete is placed or subfloor sheathing is installed. Rough plumbing, mechanical, gas and electrical inspection comes before covering, before fixtures or appliances are set, and before the framing inspection. In flood hazard areas, once the lowest floor is placed and before further vertical construction, a flood elevation certificate prepared and sealed by a registered design professional must be submitted. Frame inspection follows the roof deck or sheathing, framing, fire-blocking and bracing. Masonry is inspected before grouting cells, and lath and gypsum board before plaster or before joints and fasteners are taped and finished.
Fire-resistance-rated assemblies, smoke barriers and penetrations stay exposed until inspected. Energy inspections cover envelope insulation, fenestration, duct systems, lighting controls, heating, ventilating and air conditioning equipment and water heating. CALGreen inspections are made by a special inspector hired and paid for by the permit holder and approved by the building official, who can instead conduct them directly. The official can also accept a licensed contractor's signed self-certification for designated inspections or waive inspections for minor work.
The permit holder or agent must notify the building official when work is ready. The official can withhold an inspection if the work appears to differ from the approved plans without an approved amendment. Under Section 110.6, work cannot go past an inspection point without approval. The final inspection comes after the permitted work is complete.
Violations & Fines
Section 110.6 requires any portion of work that does not comply to be corrected, and it cannot be covered, concealed or used until the building official inspects and authorizes it. Covering required work early breaches Section 110.3. Section 114.7 treats each day of violation as a separate offense and a public nuisance, and construction-code infractions carry administrative penalties of $100, $500 and $1,000 under Section 1-7.4(c).
Frequently Asked Questions
What inspections does a Novato building permit involve?
Who requests an inspection in Novato?
Can I use the building before final inspection?
Can any inspection be skipped for minor work?
Sources & Official References
Other rules in Novato
California rules heatmap·Compare Novato to another location·View the California building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Building Inspections in Nearby Cities
How other cities in Marin County handle building inspections.