Palm Beach Gardens, FL Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Adopting section
Palm Beach Gardens Code § 86-27, Exh. A
Governing FBC section
Section 110, Inspections
First building inspection
Foundation inspection after trenching and reinforcing steel
Final inspection
Required before building is ready for occupancy
Concealment rule
No covering framing without a building official release

Summary

The Florida Building Code, locally adopted at Palm Beach Gardens Code Section 86-27, requires the building official to inspect permitted construction at set stages before work may continue or be closed up. Section 110.3 lists required inspections by trade, from foundation and slab through framing, roofing and a final inspection before occupancy, and work must stay exposed until each stage is approved.

110.1 General. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. ... 110.3 Required inspections. The building official upon notification from the permit holder or his or her agent, shall make the following inspections, and such other inspections as deemed necessary, and shall either release that portion of the construction or shall notify the permit holder or his or her agent of any violations which must be corrected in order to comply with the technical codes. The building official shall determine the timing and sequencing of when inspections occur and what elements are inspected at each inspection. ... A.Building1.Foundation inspection. To be made after trenches are excavated and forms erected and required reinforcing steel is in place ... 6.Final inspection. To be made after the building is completed and ready for occupancy.

Full Breakdown

Section 110.1 of the Florida Building Code, as locally adopted by Palm Beach Gardens Code Section 86-27, makes any permitted construction or work subject to inspection by the building official, and the permit holder must keep the work accessible and exposed until it is approved; passing an inspection does not excuse a separate code violation. Section 110.2.1 lets the building official examine existing building, electrical, gas, mechanical or plumbing systems before issuing a permit to alter, move or change occupancy, and again at any point before, during or after the permitted work.

Section 110.3 assigns the sequence: for a building, the required stops are the foundation inspection (after trenching, forms and reinforcing steel), the slab or under-floor inspection, the lintel/tie-beam and masonry inspection, the sheathing inspection covering roof, wall and floor sheathing and fasteners, the framing inspection covering window and door bucks, trusses and fire blocking, the roofing inspection covering dry-in, insulation, roof coverings and flashing, the lath/drywall inspection, and the final inspection once the building is complete and ready for occupancy. Parallel required-inspection lists apply to electrical work (underground, rough-in, low-voltage and final), plumbing (underground, rough-in and final, with Section 312 of the Florida Building Code, Plumbing governing required tests), mechanical, and gas piping, plus a site-debris cleanup requirement before final approval.

Section 110.3.3 bars covering reinforcing steel or structural framing without a building official release, and Section 110.3.5 requires shoring on threshold buildings to be designed and inspected by a Florida-licensed engineer before the threshold inspector's mandatory inspections. The building official, upon notification from the permit holder, makes each inspection and either releases that portion of construction or lists the violations that must be corrected.

Violations & Fines

Concealing work before its required inspection is itself a code violation: Section 110.3.3 forbids covering reinforcing steel or structural framing without a building official release, and general unpermitted or non-compliant construction is a misdemeanor under Section 114, with each day of continued violation a separate offense. The building official can also issue a Section 115 stop-work order halting all work immediately until conditions are corrected.

Frequently Asked Questions

Do I need to be present for a Palm Beach Gardens building inspection?
Section 110.3 says the building official makes required inspections upon notification from the permit holder or the holder's agent, and either releases that portion of the work or lists the violations that must be corrected, so the notifying party, not necessarily the homeowner personally, coordinates access.
Can I cover framing before it's inspected?
No. Section 110.3.3 requires a release from the building official before reinforcing steel or structural framing can be covered or concealed, and field welding or bolted connections must be certified to the building official on request.
What is the last inspection before I can occupy a new building?
Section 110.3(A)(6) requires a final inspection made after the building is completed and ready for occupancy, and in flood hazard areas a final lowest-floor elevation certification must be submitted as part of that same final inspection.

Sources & Official References

Other rules in Palm Beach Gardens

All Palm Beach Gardens rules

Florida rules heatmap·Compare Palm Beach Gardens to another location·View the Florida building safety overview

Get notified when Building Inspections in Palm Beach Gardens, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Palm Beach County handle building inspections.

Boca Raton, FL
Some Restrictions