San Jose, CA Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
SJMC § 24.02.520
Required stages
Foundation, slab, rough, frame, lath, final
Notice for inspection
At least 1 working day
Cover-up rule
No concealing work before approval

Summary

San Jose's building official runs permitted work through six mandatory checkpoints, foundation, slab, rough, frame, lath, and final, before a building can be occupied.

The building official, upon notification, shall make the following inspections: A. Foundation inspection. To be made after excavations for footings are complete and required reinforcing steel is in place... E. Frame inspection. To be made after the roof deck or sheathing, all framing, fire blocking and bracing are in place... G. Final inspection. To be made after finish grading and the building is completed and ready for occupancy or use.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 5 Update 3).

Full Breakdown

San Jose Municipal Code § 24.02.520 requires the building official, upon notification, to make foundation, concrete slab/under-floor, protection-of-joints, rough (plumbing/mechanical/gas/electrical), frame, lath/gypsum, and final inspections at defined construction milestones. Under § 24.02.510, it is the contractor's or work-doer's duty to notify the building official when work is ready, and the official may require at least one working day's notice. Work may not proceed past an inspected stage, and reinforcing steel or structural framing may not be covered, without the building official's approval first (§ 24.02.515). A final inspection and approval is required before any building or structure may be occupied or used.

Violations & Fines

Covering or concealing work before the required inspection and approval (e.g., pouring concrete over unapproved reinforcing steel, or closing up framing before the frame inspection) means that work must be exposed again for inspection, and reinspection fees apply under § 24.02.535 when work isn't ready or corrections weren't made.

Frequently Asked Questions

Who has to call for a San Jose building inspection?
The person doing the permitted work. SJMC § 24.02.510 makes it their duty to notify the building official when the work is ready to be inspected.
Can I cover framing before it's inspected?
No. SJMC § 24.02.515 bars covering or concealing reinforcing steel or structural framing until the building official has approved that stage.

Sources & Official References

Other rules in San Jose

All San Jose rules

California rules heatmap·Compare San Jose to another location·View the California building safety overview

Get notified when Building Inspections in San Jose, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Building Inspections in Nearby Cities

How other cities in Santa Clara County handle building inspections.

Sunnyvale, CA
Some Restrictions
Mountain View, CA
Some Restrictions